Search Legislation

The Road Works (Recovery of Costs) (Scotland) Regulations 2003

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about opening options

Opening Options

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Citation, commencement and extent

1.—(1) These Regulations may be cited as the Road Works (Recovery of Costs) (Scotland) Regulations 2003 and shall come into force on 1st October 2003.

(2) These Regulations extend to Scotland only.

Interpretation

2.  In these Regulations–

“the Act” means the New Roads and Street Works Act 1991;

“the 1992 Regulations” means the Road Works (Sharing of Costs of Works) (Scotland) Regulations 1992(1);

“chargeable job” means an item of work, the costs of which are recoverable under the provisions of Part IV of the Act;

“claimant” means an authority, body or person who is entitled to recover costs under Part IV of the Act;

“costs” means costs or expenses referred to in section 155(1) of the Act as being recoverable by an authority, body or person under Part IV of the Act;

“costs centre” means a unit of financial accountability identifiable within a claimant’s management accounts and responsible for specific activities within a claimant’s organisation;

“cost in that period of capital” means the cost of capital calculated by reference to the rate of return which is prescribed either by legislation, or by the relevant regulator in respect of the claimant’s regulated activities (whether or not the chargeable job is such an activity) or, if no such rate is prescribed, by reference to a rate which is two per cent above the Public Sector Discount Rate as set by the Treasury from time to time;

“direct costs” means those costs described in regulation 5;

“licence” means any form or authorisation, permission, or appointment, by which the claimant is authorised to carry out regulated activities;

“overheads” means those costs described in regulation 6;

“regulated activities” means activities which are authorised or regulated by a licence and

supervised by the relevant regulator;

“relevant regulator” means a person, independent of the claimant, charged with supervising the claimant’s regulated activities and ensuring a claimant complies with the terms of the licence authorising those activities; and

“support services” mean services provided from within an organisation in support of activities which incur direct costs.

Basis of recovery

3.  The basis on which the amounts of costs are to be calculated is that set out in the following provisions of these Regulations.

Costs

4.—(1) The costs shall comprise direct costs and overheads to the extent that such direct costs and overheads are relevant to a particular chargeable job and are calculated in accordance with the financial policies adopted by the claimant to state the financial results of the cost centres responsible for the chargeable job or for providing support services to such centres.

(2) Where costs are recoverable in pursuance of the 1992 Regulations the 1992 Regulations shall apply to the extent that the costs are “allowable costs” as defined in regulation 2(2) of the said Regulations.

(3) The costs shall be recoverable either as direct costs under regulation 5 or as overheads under regulation 6, but not both.

(4) The costs shall be net of any discount or rebate allowed to the claimant.

Direct Costs

5.  Direct costs are costs of any of the following descriptions:–

(a)the cost of staff (whether salaried or non-salaried) employed directly by the claimant calculated in accordance with regulation 7;

(b)the costs payable to a contractor engaged by the claimant;

(c)the cost of materials;

(d)the cost of hiring equipment, plant and vehicles for transport or, where the equipment, plant or vehicles are leased to or owned by the claimant, the equivalent cost based on relevant market rates;

(e)other costs which are relevant and specifically attributable to a chargeable job.

Overheads

6.—(1) Overheads shall comprise an appropriate percentage of the direct costs referred to in regulation 5, calculated and applied separately for each category of those costs.

(2) An appropriate percentage for the purpose of this regulation means the percentage calculated by the application of the following formula:–

where:

a

=

the total direct costs of all chargeable jobs, and jobs other than chargeable jobs, charged to the cost centre or centres responsible for the chargeable job during the most recent period for which published accounts are available;

b

=

the cost in that period of support services provided within the cost centre or centres responsible for the chargeable job;

c

=

the cost in that period of support services provided to the cost centre or centres responsible for the chargeable job by other cost centres within the claimant’s organisation; and

d

=

the cost in that period of capital and of depreciation of assets used in connection with direct costs incurred by the cost centre or centres responsible for the chargeable job, or directly or indirectly in providing support services to such cost centre or centres.

Calculation of Staff Costs and Productive Hours

7.—(1) For the purpose of regulation 5(a) above, staff costs shall be calculated by reference to the hourly rate at which a person is employed by dividing the reasonably estimated annual cost of employing a person by that person’s productive hours during the same annual period.

(2) In paragraph (1) above, “productive hours” means those hours during which it is reasonably estimated that a person is engaged on a chargeable job or work of a similar kind within the claimant’s organisation, but does not include any periods of sickness, holiday, training or other absence.

Exclusions

8.  These Regulations shall not apply to costs or expenses recoverable in respect of any action undertaken in relation to a permission granted under section 109 of the Act.

NICOL STEPHEN

A member of the Scottish Executive

St Andrew’s House, Edinburgh

8th September 2003

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents