8.—(1) At least two weeks prior to the scrapping of the vessel the applicant shall notify the Department in writing of the intended date and place of scrapping (which shall be within a member State) and the proposed method of scrapping.
(2) The vessel shall not be scrapped until the method of scrapping notified under paragraph (1) has been approved by the Department.
(3) The applicant shall before a date to be determined by the Department, furnish to the Department a declaration that the vessel has been scrapped in accordance with this Scheme.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: