Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.
11AC.—(1) Without prejudice to the generality of Article 11(1), a licence shall include such conditions as appear to the grantor to be requisite or expedient to ensure that any activity authorised by it is carried out in accordance with the requirements and prohibitions laid down by the Energy Efficiency Directive and referred to in the following paragraphs.
F2(2) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F2(3) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
F2(4) . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(5) The conditions included in a licence in accordance with paragraph (1) shall, in particular, in the case of a transmission licence include such conditions as appear to the grantor to be requisite or expedient to ensure that—
(a)in relation to network regulation and network tariffs, the requirements of Article 15(1) fourth indent of and Annex XI to the Energy Efficiency Directive are complied with;
(b)the licence holder complies with the requirements of [F3Article 15(5) third sub-paragraph] of and Annex XII to the Energy Efficiency Directive in relation to electricity from high efficiency co generation; [F4and]
(c)where Article 15(6) of the Energy Efficiency Directive requires the licence holder to be responsible for conducting balancing services and other operational services—
(i)such services are part of a service bidding process which is transparent, non discriminatory and open to scrutiny in accordance with the requirements of that provision; and
(ii)in meeting the requirements for such services and ancillary services, the licence holder complies with Article 15(8), second indent of the Energy Efficiency Directive [F5.]
F6(d). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(6) The conditions included in a licence in accordance with paragraph (1) shall in particular in the case of a distribution licence include such conditions as appear to the grantor to be requisite or expedient to ensure that—
F7(a). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(b)in relation to network regulation and network tariffs, the requirements of Article 15(1), fourth indent of and Annex XI to the Energy Efficiency Directive are complied with;
(c)the licence holder complies with the requirements of [F8Article 15(5) third sub-paragraph] and Annex XII to the Energy Efficiency Directive in relation to electricity from high efficiency co generation; [F9and]
(d)where Article 15(6) of the Energy Efficiency Directive requires the licence holder to be responsible for conducting balancing services and other operational services—
(i)such services are part of a service bidding process which is transparent, non discriminatory and open to scrutiny in accordance with the requirements of that provision; and
(ii)in meeting the requirements for such services and ancillary services, the licence holder, complies with Article 15(8), second indent of the Energy Efficiency Directive [F10.]
F11(e). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(7) The duty on the Authority in paragraph (2) to include conditions in a licence shall only have effect where the Department—
(a)has determined that it is technically possible, financially reasonable and proportionate in relation to the potential energy savings to implement a programme for the widespread provision of smart meters; and
(b)notifies the Authority in writing to that effect.
(8) In this Article—
[F12(a)"the Energy Efficiency Directive” means the European Parliament and Council Directive 2012/27/EU on energy efficiency as amended by European Parliament and Council Directive (EU) 2018/2002 and the Directive;]
(b)“smart meter” means—
(i)an electricity meter which can send and receive information using an electronic communications network; or
(ii)an electricity meter and a device which is associated with or ancillary to that meter and which enables information to be sent and received by the meter using an electronic communication network;
(c)“electronic communication” has the same meaning as in Section 4(1) of the Electronic Communications Act (Northern Ireland) 2001; and
(d)other expressions which are also used in the Energy Efficiency Directive shall have the same meaning as in that Directive.]
F1Art. 11AC inserted (25.7.2014) by Energy Efficiency Regulations (Northern Ireland) 2014 (S.R. 2014/198), reg. 8
F2Art. 11AC(2)-(4) omitted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(2)
F3Words in art. 11AC(5)(b) substituted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(3)(a)
F4Word in art. 11AC(5)(b) inserted (31.12.2020) by The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(3)(b)
F5Full stop in art. 11AC(5)(c) substituted for comma (31.12.2020) by The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(3)(c)
F6Art. 11AC(5)(d) omitted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(3)(d)
F7Art. 11AC(6)(a) omitted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(4)(a)
F8Words in art. 11AC(6)(c) substituted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(4)(b)
F9Word in art. 11AC(6)(c) inserted (31.12.2020) by The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(4)(c)
F10Full stop in art. 11AC(6)(d) substituted for comma (31.12.2020) by The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(4)(d)
F11Art. 11AC(6)(e) omitted (31.12.2020) by virtue of The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(4)(e)
F12Art. 11AC(8)(a) substituted (31.12.2020) by The Electricity (Internal Markets) Regulations (Northern Ireland) 2020 (S.R. 2020/307), regs. 1, 10(5)
The Whole Order you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Order you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Order you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.