12.—(1) Registration under section 10 of a structure or area which becomes a controlled reservoir after the relevant date must, subject to subsection (2), take place not later than 28 days after the date on which a preliminary certificate is given in relation to it for the first time (see section 47).
(2) The Department may, in relation to information or a document where it considers it appropriate to do so, extend the period of 28 days specified in subsection (1) to such other period as it may, by notice served on the reservoir manager, specify; and different periods may be specified in relation to different information or documents.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Text created by the Northern Ireland Assembly department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of the Northern Ireland Assembly.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: