Section 48 – Construction certificates
This section requires the issue of a construction certificate by the construction engineer as soon as reasonably practicable, after he or she is satisfied that the relevant works have been completed to a satisfactory standard. Subsection (2) requires the construction certificate to be issued before or not later than the final certificate. Subsection (3) requires the construction certificate to certify that the relevant works have been undertaken satisfactorily in accordance with the drawings and other specified information included along with the certificate. Subsection (4) requires the construction engineer to give the Department a copy of the certificate within 28 days of issuing it.