Section 32 – Inspection timing: other qualifications
The second special case is where a construction engineer is to be commissioned to supervise relevant works for the construction or alteration of a high or medium consequence reservoir. The construction engineer also supervises the safety of the reservoir (section 43(3)).
Where a reservoir is being discontinued or abandoned, any inspection which is due under section 30 or 31 is not required as it ceases to be a controlled reservoir on completion of the works i.e. when the final certificate is issued (subsection (1)).
Where a controlled reservoir is being constructed or altered (without being discontinued or abandoned), any inspection due under section 30 or 31 is not required; and instead inspection must be within 2 years from the date of the final certificate or at an earlier time, if recommended in the final certificate (subsection (2)).