2.—(1) The Hornsea Two Offshore Wind Farm Order 2016 is amended as follows.
(2) In paragraph 3(1) of Part 1 (Authorised Development) of Schedule 1 (Authorised Project), in the descriptions of Work No. 2A and Work No. 2B, for “up to 6 offshore HVAC collector substations”, where it occurs, substitute “up to 3 offshore HVAC collector substations”.
(3) In paragraph 3(2) of Part 1 (Authorised Development) of Schedule 1 (Authorised Project), for “must not exceed 6” substitute “must not exceed 3”.
(4) In paragraph 2(4)(b) of Part 3 (Requirements) of Schedule 1 (Authorised project), for “3,600 square metres in area or 60 metres in width” substitute “6,300 square metres in area or 90 metres in width”.
Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.
Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.
Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:
Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:
liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys