Chwilio Deddfwriaeth

The Ashton Vale to Temple Meads and Bristol City Centre Rapid Transit Order 2013

 Help about what version

Pa Fersiwn

  • Y Diweddaraf sydd Ar Gael (Diwygiedig)
  • Gwreiddiol (a wnaed Fel)

Status:

Dyma’r fersiwn wreiddiol (fel y’i gwnaed yn wreiddiol). This item of legislation is currently only available in its original format.

Retained apparatus: protection and plan approval

20.  Not less than 56 days before commencing to construct or renew any specified work, the promoter must submit to the specified undertaker plans of the works.

21.  In relation to a work which is a specified work because of its proximity to or effect on a sewer, the plans to be submitted to the specified undertaker under paragraph 20 must be detailed plans describing—

(a)the exact position of the specified work;

(b)the level at which it is proposed to be constructed or renewed;

(c)the manner of its construction or renewal;

(d)the position of all sewers within 15 metres of the specified work or upon which the specified work will impose a load; and

(e)by way of detailed drawings, every alteration proposed to be made to any such sewer.

22.  The promoter must not commence the construction or renewal of any specified work to which paragraph 20 applies until the specified undertaker has given written approval of the plans so submitted.

23.  Any approval of the specified undertaker required under paragraph 22—

(a)may be given subject to reasonable conditions for any purpose mentioned in paragraph 24;

(b)must not be unreasonably withheld; and

(c)is deemed to have been given if it is neither given nor refused within 56 days of the submission of plans for approval.

24.  In relation to a work to which paragraph 21 applies, the specified undertaker may require such modifications to be made to the plans as may be reasonably necessary for the purpose of securing its sewerage system against interference or risk of damage or for the purpose of providing or securing proper and convenient means of access to any sewer.

25.  A specified work is to be constructed (and in the case of any temporary work removed) only in accordance with—

(a)the approved plans (and, in the case of plans relating to sewers approved, deemed to have been approved or settled by arbitration, as amended from time to time by agreement between the promoter and the specified undertaker); and

(b)all reasonable requirements made by the specified undertaker for the alteration, or otherwise for the protection, of the apparatus, or for securing access to it.

and an officer of the specified undertaker is entitled to watch and inspect the carrying out of the work.

26.  If within 42 days after the submission to it of any plans under paragraph 20, in consequence of the works proposed by the promoter the specified undertaker reasonably requires the removal of any apparatus and gives written notice to the promoter of that requirement, the foregoing provisions of this Schedule have effect as if the removal of such apparatus had been required by the specified undertaker under paragraph 8.

27.  Nothing in paragraph 20 or 26 precludes the promoter from submitting at any time, or from time to time, but in no case less than 28 days before commencing the construction of any specified work, a new plan in place of the plan previously submitted, in which case the provisions of those paragraphs apply to, and in respect of, such new plan except that the reference in paragraph 26 to 42 days is to be treated as a reference to 21 days.

28.  The promoter is not required to comply with paragraph 20 in a case where it is necessary to carry out emergency works but, in such a case, it must give to the specified undertaker notice as soon as reasonably practicable, and a plan of the works as soon as reasonably practicable afterwards, and must comply with paragraph 25 so far as reasonably practicable in the circumstances.

29.  Nothing in paragraph 28 entitles the promoter to carry out works to any apparatus but, upon receipt of notice from the promoter, the specified undertaker must proceed to carry out such works as may be required without unnecessary delay.

Yn ôl i’r brig

Options/Help

Print Options

Close

Mae deddfwriaeth ar gael mewn fersiynau gwahanol:

Y Diweddaraf sydd Ar Gael (diwygiedig):Y fersiwn ddiweddaraf sydd ar gael o’r ddeddfwriaeth yn cynnwys newidiadau a wnaed gan ddeddfwriaeth ddilynol ac wedi eu gweithredu gan ein tîm golygyddol. Gellir gweld y newidiadau nad ydym wedi eu gweithredu i’r testun eto yn yr ardal ‘Newidiadau i Ddeddfwriaeth’.

Gwreiddiol (Fel y’i Deddfwyd neu y’i Gwnaed): Mae'r wreiddiol fersiwn y ddeddfwriaeth fel ag yr oedd pan gafodd ei deddfu neu eu gwneud. Ni wnaed unrhyw newidiadau i’r testun.

Close

Dewisiadau Agor

Dewisiadau gwahanol i agor deddfwriaeth er mwyn gweld rhagor o gynnwys ar y sgrin ar yr un pryd

Close

Rhagor o Adnoddau

Gallwch wneud defnydd o ddogfennau atodol hanfodol a gwybodaeth ar gyfer yr eitem ddeddfwriaeth o’r tab hwn. Yn ddibynnol ar yr eitem ddeddfwriaeth sydd i’w gweld, gallai hyn gynnwys:

  • y PDF print gwreiddiol y fel deddfwyd fersiwn a ddefnyddiwyd am y copi print
  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • slipiau cywiro
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill
Close

Rhagor o Adnoddau

Defnyddiwch y ddewislen hon i agor dogfennau hanfodol sy’n cyd-fynd â’r ddeddfwriaeth a gwybodaeth am yr eitem hon o ddeddfwriaeth. Gan ddibynnu ar yr eitem o ddeddfwriaeth sy’n cael ei gweld gall hyn gynnwys:

  • y PDF print gwreiddiol y fel gwnaed fersiwn a ddefnyddiwyd am y copi print
  • slipiau cywiro

liciwch ‘Gweld Mwy’ neu ddewis ‘Rhagor o Adnoddau’ am wybodaeth ychwanegol gan gynnwys

  • rhestr o newidiadau a wnaed gan a/neu yn effeithio ar yr eitem hon o ddeddfwriaeth
  • manylion rhoi grym a newid cyffredinol
  • pob fformat o’r holl ddogfennau cysylltiedig
  • dolenni i ddeddfwriaeth gysylltiedig ac adnoddau gwybodaeth eraill