Section 41 – Termination of supervision by construction engineer
67.This section makes it clear that the obligation of a reservoir manager to appoint a construction engineer in respect of relevant works to a controlled reservoir comes to an end when the engineer gives a copy of the final certificate to SEPA in accordance with Section 39(9). This step marks the normal end-point for the involvement of a construction engineer in relation to the relevant works.