Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
14.—(1) A person who is minded to make an EIA application may ask the relevant planning authority [F1or specified person] to state their opinion as to the scope and level of detail of the information to be provided in the environmental statement (“scoping opinion”).
(2) A request under paragraph (1) must include—
(a)in relation to an application for planning permission—
(i)a plan sufficient to identify the land;
(ii)a brief description of the nature and purpose of the development including its location and technical capacity;
(iii)its likely significant effects on the environment; and
(iv)such other information or representations as the person making the request may wish to provide or make;
(b)in relation to a subsequent application—
(i)a plan sufficient to identify the land;
(ii)sufficient information to enable the relevant planning authority [F2or specified person] to identify any planning permission [F2or infrastructure consent order] granted for the development in respect of which a subsequent application has been made;
(iii)a description of the likely significant effects on the environment which were not identified at the time planning permission was granted; and
(iv)such other information or representations as the person making the request may wish to provide or make.
(3) An authority [F3or specified person] receiving a request under paragraph (1) must, if they consider that they have not been provided with sufficient information to adopt a scoping opinion, notify the person who made the request of the points on which they require additional information.
(4) An authority [F4or specified person] must not adopt a scoping opinion in response to a request under paragraph (1) until they have consulted the consultees, but must, subject to paragraph (5), within 8 weeks beginning with the date of receipt of that request or such longer period as may be agreed in writing with the person who made the request, adopt a scoping opinion and send a copy to the person who made the request.
(5) Where a person has, at the same time as making a request for a screening opinion under regulation 6(1), asked the authority [F5or specified person] for an opinion under paragraph (1) above, and the authority [F5or specified person] have adopted a screening opinion to the effect that the development is EIA development, the authority [F5or specified person] must, within 8 weeks beginning with the date on which that screening opinion was adopted or such longer period as may be agreed in writing with the person who made the request, adopt a scoping opinion and send a copy to the person who made the request.
[F6(5A) Where a specified person adopts a scoping opinion they must send a copy to the Welsh Ministers and any planning authority in whose area the development will take place.]
(6) Before adopting a scoping opinion the authority [F7or specified person] must take into account—
(a)any information provided by the applicant about the proposed development;
(b)the specific characteristics of the particular development;
(c)the specific characteristics of development of the type concerned; and
(d)the environmental features likely to be significantly affected by the development.
(7) Where an authority [F8or specified person] fail to adopt a scoping opinion within the relevant period mentioned in paragraph (4) or (5), the person who requested the opinion may ask the Welsh Ministers under regulation 15(1) to make a direction as to the information to be provided in the environmental statement (a “scoping direction”).
(8) Paragraph (7) applies even if the authority [F9or specified person] has not received additional information which they have sought under paragraph (3).
(9) Nothing prevents an authority [F10or specified person] which have adopted a scoping opinion from requiring the person who made the request to provide additional information.
(10) “Additional information” (“gwybodaeth ychwanegol”) in paragraph (9) means information in connection with any statement that may be submitted by that person as an environmental statement for the purposes of these Regulations in connection with an application for planning permission or a subsequent application for the same development.
Textual Amendments
F1Words in reg. 14(1) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(a) (with reg. 12(44))
F2Words in reg. 14(2)(b)(ii) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(b) (with reg. 12(44))
F3Words in reg. 14(3) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(c) (with reg. 12(44))
F4Words in reg. 14(4) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(d) (with reg. 12(44))
F5Words in reg. 14(5) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(e) (with reg. 12(44))
F6Reg. 14(5A) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(f) (with reg. 12(44))
F7Words in reg. 14(6) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(g) (with reg. 12(44))
F8Words in reg. 14(7) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(h) (with reg. 12(44))
F9Words in reg. 14(8) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(i) (with reg. 12(44))
F10Words in reg. 14(9) inserted (15.12.2025) by The Infrastructure (Wales) Act 2024 (Consequential, Transitional, Revocation and Saving Provisions) Regulations 2025 (S.I. 2025/1192), regs. 1(2)(b), 12(13)(j) (with reg. 12(44))
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: