- Latest available (Revised)
- Original (As made)
There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Hornsea Four Offshore Wind Farm Order 2023. Any changes that have already been made by the team appear in the content and are referenced with annotations.
Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
Commencement Information
I1Sch. 15 Pt. 3 in force at 3.8.2023, see art. 1
(1) Examination Library Reference | (2) Document Name | (3) Version | (4) Date |
---|---|---|---|
APP-213 | the access to works plan | 1 | 8 October 2021 |
REP7-049 | the book of reference | 4 | 10 August 2022 |
REP5-084 | the Bridge protected area plan | 1 | 20 June 2022 |
REP6-008 | the commitments register | 3 | 27 July 2022 |
APP-221 | the crown land plans – onshore and offshore | 1 | 8 October 2021 |
REP7-027 | the guillemot and razorbill compensation plan | 3 | 10 August 2022 |
APP-252 | the HVAC booster station lighting plan | 1 | 8 October 2021 |
Post-examination G14.2 | Johnston protective provisions plan | 1 | 16 May 2023 |
REP5-016 | the kittiwake compensation plan | 2 | 20 June 2022 |
APP-210 | the land plans | 1 | 8 October 2021 |
REP5-008 | the layout principles | 3 | 20 June 2022 |
APP-206 | the location plans – Offshore | 1 | 8 October 2021 |
APP-207 | the location plans - Onshore | 1 | 8 October 2021 |
REP7-106 | the NEO protective provisions plan, Appendix B | 1 | |
APP-208 | the offshore Order limits and grid coordinates plan | 1 | 8 October 2021 |
REP5-037 | the offshore works plans | 2 | 20 June 2022 |
APP-040 | the onshore crossing schedule | 1 | 8 October 2021 |
APP-209 | the onshore Order limits plan | 1 | 8 October 2021 |
REP5-038 | the onshore works plans | 2 | 20 June 2022 |
Post-examination | the outline cable specification and installation plan | 5 | 17 April 2023 |
REP4-019 | the outline code of construction practice | 3 | 10 May 2022 |
REP4-019 | the outline construction traffic management plan | 3 | 10 May 2022 |
REP4-021 | the outline design plan | 2 | 10 May 2022 |
REP1-029 | the outline ecological management plan | 2 | 8 March 2022 |
APP-253 | the outline employment and skills plan | 1 | 8 October 2021 |
REP2-029 | the outline energy balancing infrastructure HazID report | 2 | 29 March 2022 |
APP-249 | the outline enhancement strategy | 1 | 8 October 2021 |
REP1-033 | the outline fisheries coexistence and liaison plan | 2 | 8 March 2022 |
REP3-010 | the outline landscape management plan | 4 | 21 April 2022 |
REP6-011 | the outline marine mammal mitigation protocol | 2 | 27 July 2022 |
REP7-058 | the outline marine monitoring plan | 7 | 10 August 2022 |
REP5-042 | the outline marine written scheme of investigation | 2 | 20 June 2022 |
APP-251 | the outline net gain strategy | 1 | 8 October 2021 |
APP-241 | the outline onshore infrastructure drainage strategy | 1 | 8 October 2021 |
Post examination | the outline offshore operations and maintenance plan | 3 | 17 April 2023 |
APP-254 | the outline ornithological monitoring plan | 1 | 8 October 2021 |
REP7-054 | the outline southern north sea special area of conservation site integrity plan | 2 | 10 August 2022 |
REP3-012 | the outline written scheme of investigation for onshore archaeology | 2 | 21 April 2022 |
REP6-006 | the pro-rata annex | 4 | 27 July 2022 |
APP-215 | the public rights of way plan | 1 | 8 October 2021 |
APP-214 | the streets plan | 1 | 8 October 2021 |
APP-220 | the tree preservation order and hedgerow plan | 1 | 8 October 2021 |
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: