Search Legislation

The Bridgwater Tidal Barrier Order 2022

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

Supplementary powers and provisions

Agreements with owners of land and others for construction of works

16.—(1) The Agency may enter into and carry into effect agreements or arrangements with the Harbour Authority and the owners of, or other persons interested in, any land—

(a)in or through which any of the authorised works are or may be constructed, or

(b)the drainage of which may be affected by the construction of any of the authorised works, for or with respect to the doing of anything which may be necessary in order to carry out, or in consequence of, the authorised works.

(2) Without limitation on the scope of paragraph (1), any such agreement may provide for—

(a)the payment by the Agency of, or the making of contributions by it towards, the cost incurred, or to be incurred, by the Harbour Authority and any such owners or other persons in or in connection with the doing of any such thing, or

(b)the payment by the Agency of compensation for any injury suffered or loss incurred by the Harbour Authority and any such owners or other persons by reason or in consequence of the execution by the Agency of the authorised works, or entry upon land.

Temporary closing of river in connection with works

17.—(1) Regardless of anything in any other enactment or in any rule of law, the Agency may temporarily close the river or any part of it within the Order limits, to navigation during or for the purposes of executing any works or doing anything authorised by or under this Order.

(2) In exercising the powers conferred by paragraph (1), the Agency must seek to minimise interference with navigation on the river so far as is reasonably practicable and consistent with the efficient and economical execution of the works.

(3) Subject to paragraph 10 of Schedule 10 (protection of Port of Bridgwater) neither the Agency nor the Harbour Authority is liable for any costs, damages or expenses whatsoever incurred by any person as a result, directly or indirectly, of any closure of the river under paragraph (1).

Diversion of flow of water

18.—(1) The Agency may by means of the authorised works divert, intercept, stop up or otherwise interfere with the waters of, or the flow of water in, the river system.

(2) In paragraph (1) “the river system” means the river, Wildmarsh Rhyne, Pim’s Pill Reach, Pippin’s Rhyne, Fenlyn’s Rhyne, Cannington Brook, South Moor Main Brook, River Yeo, Sowy River, River Isle, Witcombe Bottom Main Drain, the River Tone and the Bridgwater and Taunton Canal together with any unnamed drainage tributaries of these rivers.

Power to take, pump, impound and discharge water

19.—(1) The Agency may, in connection with the construction or maintenance of the works—

(a)take, impound and use water from, and discharge water into, the river;

(b)pump any water required by it from or into the river;

(c)pump any water found by it into the river or into any watercourse, public sewer, or drain.

(2) For the purposes set out in paragraph (1), the Agency may—

(a)lay down, take up and alter conduits, pipes and other works and conveniences;

(b)on any land within the Order Limits, make openings into, and connections with, the river, or any watercourse, public sewer or drain.

(3) The Agency must take such steps as are reasonably practicable to secure that any water discharged into a watercourse or public sewer or drain in exercise of the powers conferred by this article is as free as may be practicable from gravel, soil or other solid substance or oil or matter in suspension.

(4) Any dispute arising from the exercise of the powers conferred by paragraph (1) to connect to or use a public sewer or drain is to be determined as if it were a dispute under section 106 of the Water Industry Act 1991(1) (right to communicate with public sewers).

(5) The Agency must not, in exercise of the powers conferred by paragraphs (1) and (2)—

(a)discharge any water into any public sewer or drain except with the consent (which is not to be unreasonably withheld) of the person to whom it belongs and subject to such terms and conditions as that person may reasonably impose;

(b)make any opening into any public sewer or drain except in accordance with plans reasonably approved by and under the superintendence (if provided) of the person to whom the sewer or drain belongs.

(6) If a person who receives an application for consent or approval fails to notify the Agency of a decision within 28 days of receiving the application for consent under sub-paragraph (3)(a) or approval under sub-paragraph (5)(b) then that person is deemed to have granted consent or approval, as the case may be.

(7) Nothing in this article obviates any requirement for an environmental permit under regulation 12(1)(b) of the Environmental Permitting (England and Wales) Regulations 2016(2) (requirement for an environmental permit).

(8) In this article—

(a)public sewer or drain” means a sewer or drain which belongs to a sewerage undertaker, the Agency, a harbour authority, an internal drainage board, a local authority, or a joint planning board, and

(b)expressions used both in this article and in the Water Resources Act 1991(3) have the same meaning as in that Act, other than “public sewer or drain” or “watercourse”.

(9) In paragraph (8), “internal drainage board” has the same meaning as in Part 1 of the Land Drainage Act 1991(4).

Water abstraction and impounding

20.—(1) The restriction imposed by section 24(1) of the Water Resources Act 1991(5) (restrictions on abstraction) does not apply in relation to the abstraction of water for the purposes of, or in connection with, the construction of the authorised works.

(2) Section 25 of the Water Resources Act 1991(6) (restrictions on impounding) does not apply in relation to anything done in the exercise of the powers conferred by this Order with respect to the authorised works.

(3) Section 48A(1) of the Water Resources Act 1991(7) (civil remedies for loss or damage due to water abstraction) does not apply in relation to the abstraction of water in connection with the exercise of the powers conferred by this Order.

(4) Where—

(a)the Agency causes loss or damage to another person by the abstraction of water in connection with the exercise of the powers conferred by this Order, and

(b)the circumstances are such that, but for paragraph (3), causing the loss or damage would have constituted breach of the duty under section 48A(1) of the Water Resources Act 1991, the Agency must compensate the other person for the loss or damage.

(5) Compensation under paragraph (4) is to be assessed on the same basis as damages for the breach of the duty under section 48A(1) of the Water Resources Act 1991.

(6) Section 48A(5) of the Water Resources Act 1991 (prohibition of claims in respect of loss or damage caused by abstraction of water which are not claims under that section) has no application to claims under this article.

(7) In this article, “abstraction” has the same meaning as in the Water Resources Act 1991.

Protective works

21.—(1) Subject to the following provisions of this article, the Agency may at its own expense, carry out such protective works to any building lying within the Order limits as the Agency considers to be necessary or expedient.

(2) Protective works may be carried out—

(a)at any time before or during the construction in the vicinity of the building of any part of the authorised works; or

(b)after the completion of the construction of that part of the authorised works, at any time up to the end of the period of 5 years beginning with the day on which that part of the authorised works is first opened for use.

(3) For the purposes of determining how the powers under this article are to be exercised the Agency may (subject to paragraph (5)) enter and survey any building falling within paragraph (1) and any land within its curtilage and place on, leave on and remove from the land monitoring apparatus.

(4) For the purposes of carrying out protective works under this article to a building the Agency may (subject to paragraphs (5) and (6)) with all necessary plant and equipment—

(a)enter the building and any land within its curtilage, and

(b)where the works cannot be carried out reasonably conveniently without entering land adjacent to the building, enter the adjacent land (but not any building erected on it),

and in either case the Agency may take exclusive possession of the building and land if this is reasonably required for the purpose of carrying out the protective works.

(5) Before exercising—

(a)a right under paragraph (1) to carry out protective works to a building;

(b)a right under paragraph (3) to enter a building;

(c)a right under paragraph (4)(a) to enter and take possession of a building or land, or

(d)a right under paragraph (4)(b) to enter and take possession of adjacent land,

the Agency must, except in the case of emergency, serve on the owners and occupiers of the building or land not less than 14 days’ notice of its intention to exercise that right and, in a case falling within sub-paragraph (a) or (c), specifying the protective works proposed to be carried out.

(6) Where notice is served under paragraph (5), the owner or occupier of the building or land concerned may, by serving a counter-notice within the period of 10 days beginning with the day on which the notice was served, require the question as to whether it is necessary or expedient to carry out the protective works or to enter and take possession of the building or land to be referred to arbitration under article 68 (arbitration).

(7) The Agency must compensate the owners and occupiers of any building or land in relation to which the powers conferred by this article have been exercised for any loss or damage arising to them by reason of the exercise of those powers.

(8) The Agency must compensate the owners and occupiers of a building for any damage sustained by them where—

(a)protective works are carried out under this article to the building, and

(b)within the period of 5 years beginning with the latter of—

(i)the day on which those parts of the authorised works constructed within the vicinity of the building first open for use, or

(ii)the day on which completion of the protective works takes place,

it appears that the protective works are inadequate to protect the building against damage caused by the construction or operation of that part of the works.

(9) Without affecting article 69 (no double recovery), nothing in this article relieves the Agency from any liability to pay compensation under section 10(2) of the 1965 Act (further provision as to compensation for injurious affection).

(10) Any compensation payable under paragraph (7) or (8) is to be determined, in case of dispute, under Part 1 of the 1961 Act.

(11) In this article “protective works”, in relation to a building, means—

(a)underpinning, strengthening and any other works the purpose of which is to prevent damage which may be caused to the building by the construction, maintenance or operation of the authorised works;

(b)any works the purpose of which is to remedy any damage which has been caused to the building by the construction, maintenance or operation of the authorised works;

(c)any works the purpose of which is to secure the safe operation of the authorised works or to prevent or minimise the risk of such operation being disrupted.

Planning permission

22.  Any planning permission which is deemed by a direction given under section 90(2A) of the 1990 Act(8) (development with government authorisation) to be granted in relation to the authorised works is to be treated as specific planning permission for the purposes of section 264(3)(a) of that Act (cases in which land is to be treated as operational land).

Power to survey and investigate land, etc.

23.—(1) The Agency may for the purposes of this Order and in respect of land lying within the Order limits—

(a)survey or investigate any such land;

(b)without limitation on the scope of sub-paragraph (a), make trial holes in such positions as the Agency thinks fit on such land to investigate the nature of the surface layer and subsoil and remove soil samples;

(c)without limitation on the scope of sub-paragraph (a), carry out ecological or archaeological investigations on such land;

(d)take steps to protect or remove any flora or fauna on such land where the flora or fauna may be affected by the carrying on of the authorised works;

(e)place on, leave on and remove from such land apparatus for use in connection with the exercise of any of the powers conferred by sub-paragraphs (a) to (d);

(f)enter on such land for the purpose of exercising any of the powers conferred by sub-paragraphs (a) to (e).

(2) No land may be entered, or equipment placed or left on or removed from the land under paragraph (1), unless at least 7 days’ notice has been served on every owner and occupier of the land.

(3) Any person entering land under this article on behalf of the Agency—

(a)must, if so required, before or after entering the land produce written evidence of authority to do so, and

(b)may take onto the land such vehicles and equipment as are necessary to carry out the survey or investigation or to make trial holes.

(4) No trial holes are to be made under this article—

(a)in a carriageway or footway without the consent of the highway authority;

(b)in a private street without the consent of the street authority,

but such consent must not be unreasonably withheld.

(5) If either a highway authority or a street authority which receives an application for consent under paragraph (4) fails to notify the Agency of its decision within 14 days of receiving the application, that authority is deemed to have granted consent.

(6) The Agency must compensate the owners and occupiers of the land for any loss or damage arising by reason of the exercise of the powers conferred by this article, such compensation to be determined, in case of dispute, under Part 1 of the 1961 Act.

Felling or lopping of trees

24.—(1) The Agency may fell or lop any trees or shrub near any part of the authorised works, or cut back its roots, if it reasonably believes it to be necessary to do so to prevent the tree or shrub—

(a)from obstructing or interfering with the construction, maintenance or operation of the authorised works or any apparatus used on the authorised works;

(b)from constituting a danger to persons using the authorised works.

(2) In exercising the powers conferred by paragraph (1), the Agency—

(a)must not cause unnecessary damage to any tree or shrub, and

(b)must pay compensation to any person for any loss or damage arising from the exercise of those powers.

(3) Any dispute as to a person’s entitlement to compensation under paragraph (2)(b), or as to the amount of compensation, is to be determined under Part 1 of the 1961 Act.

(1)

Section 106 was amended by sections 35(8) and 43(2) of the Competition and Services (Utilities) Act 1992 (c. 43), by section 99 of the Water Act 2003 (c. 37), and by paragraph 16(1) of Schedule 3 to the Flood and Water Management Act 2010 (c. 29).

(2)

S.I. 2016/1154, to which there are amendments not relevant to this Order.

(5)

Section 24(1) was amended by S.I. 1996/593, 2013/755 (W 90).

(6)

Section 25 was amended by section 2 of the Water Act 2003 (c. 37) and S.I. 2013/755 (W 90), 2015/664.

(7)

Section 48A was inserted by section 24(1) of the Water Act 2003.

(8)

Section 90(2A) was inserted by section 16(1) of the Transport and Works Act 1992 (c. 42).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources