Review of registration following notification of a change in circumstances

14.—(1) This regulation applies where—

(a)the Authority receives a notification under regulation 10(1)(d), (g) or (l), and

(b)regulation 15 (change of producer of biomethane) does not apply.

(2) On receipt of the notification, the Authority may—

(a)require the participant to provide such information as the Authority considers necessary to enable the Authority to consider whether a review should be carried out in accordance with this regulation and, if appropriate, to carry out such a review, and

(b)review the registration of the participant to which the notification relates to ensure that they continue to meet the requirements under these Regulations.

(3) No periodic support payment may be made from the date on which the Authority receives the notification until the Authority has notified the participant that—

(a)it is satisfied that it is not necessary to review the registration of the participant, or

(b)it has carried out a review and is satisfied that the participant may continue to be registered.

(4) Where the Authority is satisfied in accordance with paragraph (3) it must resume payment of periodic support payments in accordance with these Regulations and pay to the participant any periodic support payments withheld in accordance with paragraph (3).

Change of producer of biomethane

15.—(1) This regulation applies where—

(a)a person begins to use equipment used to produce biomethane (the “new producer”), and

(b)a participant (the “original producer”) is receiving periodic support payments for the production of biomethane for injection using that same equipment used to produce biomethane.

(2) No periodic support payment may be made to the new producer until—

(a)the new producer has notified the Authority of the change,

(b)injection of biomethane produced by the new producer has commenced, and

(c)the steps set out in paragraph (4) have been completed.

(3) On receipt of a notification under paragraph (2)(a), the Authority may require the new producer to provide such information as the Authority considers necessary for the proper administration of the Scheme.

(4) Where the Authority is satisfied that the ongoing participant obligations will continue to be complied with by the new producer, the Authority must (subject to regulation 7 (treatment of grants from public finds) and 32(4) (revocation of registration))—

(a)update the central register by substituting the name of the new producer, and

(b)give the new producer a written statement including such of the following information as the Authority considers applicable—

(i)the date of registration of the original producer,

(ii)the date on which the new producer is added to the central register,

(iii)any tariff which applies,

(iv)the process and timing for providing meter readings,

(v)details of the frequency and timetable for periodic support payments,

(vi)the tariff lifetime and tariff end date,

(vii)the ongoing participant obligations, and

(viii)any conditions attached to the registration of the original producer as a participant.

(5) The Authority may refuse to register a new producer where it considers that one or more of the applicable ongoing participant obligations, or one or more of the conditions attached to the registration of the original producer as a participant, will not be complied with.

(6) Where the new producer is registered—

(a)the new producer must be paid periodic support payments (calculated from the date of receipt of the notification under paragraph (2) until the tariff end date in accordance with these Regulations), and

(b)the original producer must not be paid periodic support payments in relation to any biomethane for which payments are made under sub-paragraph (a).

(7) This paragraph applies where, within the period of 12 months beginning with a change of producer, the Authority becomes aware that a new producer is using equipment used to produce biomethane and the original producer is receiving periodic support payments for the production of biomethane for injection using that same equipment used to produce biomethane, and—

(a)no notification is made in accordance with paragraph (2)(a), or

(b)any information required under paragraph (3) is not provided to the Authority.

(8) Where paragraph (7) applies, at the end of the period of 12 months specified in that paragraph—

(a)the Authority must revoke the participant’s registration, and

(b)no further periodic support payments may be made in respect of any biomethane produced using that equipment used to produce biomethane.

(9) The period specified in paragraph (8) may be extended by the Authority where the Authority considers it is just and equitable to do so.

Withdrawal of participant

16.—(1) A participant may notify the Authority that they intend to withdraw from the Scheme.

(2) Notification given under paragraph (1) must state the date on which the participant intends to withdraw from the Scheme (“the withdrawal date”), which must be no earlier than 28 days after the date on which the notification is given.

(3) The participant ceases to be a participant, and ceases to be entitled to the payment of periodic support payments, on the withdrawal date.

(4) The Authority must update the central register by recording that the participant has withdrawn from the Scheme, together with the withdrawal date.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources