Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
4.—(1) Article 3 is amended as follows.
(2) In paragraph 1—
(a)in the first subparagraph—
(i)for “to which free allocation has been given, in accordance with Article 10a of Directive 2003/87/EC, for the trading period from 2021 until 2030” substitute “ that are FA installations ”;
(ii)after “its submission.” insert “ In 2026 this report must include data for the 2 years preceding its submission if the operator is not required under this Article to submit in 2025 a report including data for 2024. ”;
(b)omit the second subparagraph.
(3) In paragraph 2—
(a)in the first subparagraph—
(i)after “must” insert “ be verified as satisfactory in accordance with the Verification Regulation 2018 and ”;
(ii)omit “on the structure of the group, if any, to which the installation belongs and”;
(iii)for “to operate” substitute “ operation ”;
(b)omit the second subparagraph.
(4) In paragraph 3—
(a)in the first subparagraph for the words from “by 31 March” to “submission” substitute “ to the regulator on or before 30 June in the 2021 scheme year and on or before 31 March in each subsequent scheme year ”;
(b)omit the second to fifth subparagraphs.
(5) In paragraph 4—
(a)for “competent authority” in each place substitute “ regulator ”;
(b)in the first subparagraph—
(i)in point (a)—
(aa)omit “verified”;
(bb)omit “and the issuance of the allowances has not been suspended”;
(ii)in point (c) after “verified” insert “ as satisfactory ”;
(c)omit the second subparagraph (that is to say, the words from “The competent authority shall not” to “point (a).”).
(6) After paragraph 4 insert—
“5. Where the regulator makes an estimate of the value of a parameter under paragraph 4, the regulator must give notice of the value to the operator
6. Subject to paragraph 8, where notice of an estimate of the value of a parameter is given, for the purposes of this Regulation, the operator must be treated as having submitted an activity level report including the estimated value.
7. Where, after making an estimate of a parameter (including a rectified estimate, or a further rectified estimate, made under this paragraph), the regulator considers that there is an error in the estimate, the regulator must:
(a)withdraw any notice of the estimate given under paragraph 5;
(b)make a rectified estimate; and
(c)give notice of the rectified estimate in accordance paragraph 5,
and paragraph 6 applies to a notice of the rectified estimate as it does to the notice of the previous estimate.
8. Where no activity level report has been submitted by the operator of an installation by the time limit referred to in paragraph 3 and the regulator makes an estimate of the value of a parameter under paragraph 4(a):
(a)Article 3a does not apply;
(b)the regulator must not send to the UK ETS authority under Article 6a(2) any adjustment to free allocation calculated on the basis of such an estimate, or any recalculation of the preliminary or final annual number of allowances to be allocated in respect of the installation calculated on the basis of such an estimate, if the effect of the adjustment is to increase the final annual number of allowances to be allocated.”.
Commencement Information
I1Sch. 2 para. 4 in force at 31.12.2020 on IP completion day, see art. 2(2)(b)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: