Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
9. For Article 5 substitute—
1. The operator of an installation at which a regulated activity is carried out and for which a greenhouse gas emissions permit (including a greenhouse gas emissions permit within the meaning of GGETSR 2012) issued for the first time is in force may apply to the regulator:
(a)for free allocation in the 2021-2025 allocation period, if the permit is issued in the period beginning on 1 July 2019 and ending on 30 June 2024;
(b)for free allocation in the 2026-2030 allocation period, if the permit is issued in the period beginning on 1 July 2024 and ending on 30 June 2029.
2. An application may be made at any time after the end of the year in which the start of normal operation occurs.
3. But where an installation has not been operating for a full calendar year after the start of normal operation, an application may not be made unless:
(a)in the case of an application under paragraph 1(a), the start of normal operation is on or after 1 January 2021;
(b)in the case of an application under paragraph 1(b), the start of normal operation is on or after 1 January 2026.
4. For the purposes of the application, the operator must divide the installation into sub-installations in accordance with Article 10.
5. The application must set out the start of normal operation and be accompanied by:
(a)a new entrant data report, verified in accordance with the Verification Regulation 2018, containing each parameter set out in sections 1 and 2 of Annex 4 for each sub-installation separately from the start of normal operation until the end of the year before the year in which the application is made;
(b)a monitoring methodology plan in accordance with Article 8 and Annex 6;
(c)the verification report on the new entrant data report, which must contain the confirmation relating to the monitoring methodology plan referred to in Article 27(3)(f) of the Verification Regulation 2018.
6. The regulator:
(a)must assess the new entrant data report and the verification report to ensure conformity with the requirements of this Regulation;
(b)where appropriate, may request corrections by the operator of any non-conformity or error that impacts on the determination of activity levels;
(c)must not determine historical activity levels under Article 17, activity levels for the purpose of Article 18(2) or calculate the preliminary or final annual number of allowances under Article 18 or 18a unless:
(i)the regulator considers that the date set out in the application as the start of normal operation, or such other date proposed by the operator, is accurate;
(ii)the data relating to the installation has been verified as satisfactory or, where it has not been verified as satisfactory, the regulator considers that any data gaps referred to in the verifier's opinion are due to exceptional and unforeseeable circumstances that could not have been avoided even if all due care had been exercised; and
(iii)any corrections requested under point (b) have been made.”.
Commencement Information
I1Sch. 1 para. 9 in force at 31.12.2020 on IP completion day, see art. 2(2)(a)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: