Obtaining hospital or small emitter status for 2026-2030 allocation period: Conditions A, B and C

This section has no associated Explanatory Memorandum

6.—(1) This paragraph applies for the purposes of paragraph 5.

Condition A

(2) Condition A is that the installation—

(a)is an installation that primarily provides services to a hospital in the 2023 scheme year; or

(b)if a regulated activity has not begun to be carried out at the installation at the date of the application—

(i)a regulated activity will begin to be carried out at the installation before 1st November 2025; and

(ii)the installation will be an installation that primarily provides services to a hospital after that date.

(3) Where the operator submits evidence that the installation meets condition A, the operator must also submit—

(a)if a regulated activity begins to be carried out at the installation on or before 1st January 2021, evidence of—

(i)the installation’s reportable emissions in each of the 2021, 2022 and 2023 scheme years, verified as mentioned in paragraph 5(6);

(ii)where the activity referred to in column 1 of the first entry in table C in Schedule 2 (combustion of fuels) is carried out at the installation, the installation’s rated thermal input in each of those years;

(b)in any other case—

(i)where a regulated activity has begun to be carried out at the installation at the date of the application, such evidence of the matters referred to in paragraph (a)(i) and (ii) as is available at the date of the application; and

(ii)where the evidence submitted under sub-paragraph (i) does not include evidence of reportable emissions for a complete scheme year, an estimate of the installation’s reportable emissions in the 2026 scheme year.

Condition B

(4) Condition B is that—

(a)a regulated activity begins to be carried out at the installation on or before 1st January 2021;

(b)the installation’s reportable emissions in each of the 2021, 2022 and 2023 scheme years do not exceed the maximum amount; and

(c)where the activity referred to in column 1 of the first entry in table C in Schedule 2 (combustion of fuels) is carried out at the installation, the installation’s rated thermal input is below 35 megawatts in each of those years.

Condition C

(5) Condition C is that—

(a)if a regulated activity is carried out at the installation at the date of the application, the regulated activity began to be carried out at the installation after 1st January 2021;

(b)if a regulated activity has not begun to be carried out at the installation at the date of the application, a regulated activity will begin to be carried out at the installation before 1st November 2025;

(c)the installation’s reportable emissions—

(i)are not likely to exceed the maximum amount in each of the scheme years in the 2026-2030 allocation period; and

(ii)if a regulated activity has begun to be carried out at the installation at the date of the application, do not exceed the maximum amount in each of the scheme years for which, at the date of the application, evidence of reportable emissions is available; and

(d)where the activity referred to in column 1 of the first entry in table C in Schedule 2 (combustion of fuels) is carried out at the installation, the installation’s rated thermal input—

(i)is likely to be below 35 megawatts in each of the scheme years in the 2026-2030 allocation period; and

(ii)if a regulated activity has begun to be carried out at the installation at the date of the application, is below 35 megawatts in each of the scheme years for which, at the date of the application, evidence of rated thermal input is available.

(6) Where the evidence submitted under sub-paragraph (5) does not include evidence of reportable emissions for a complete scheme year, the operator must also submit an estimate of the installation’s reportable emissions in the 2026 scheme year.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources