27.—(1) Following construction of the over-run areas comprised within Work No. 4 and Work. No. 5, the undertaker will at its own cost and expense and insofar as it is the owner of and/or the highway authority for the areas in question—
(a)keep the over-run areas clear of, without limitation, all rubbish, debris and vehicles, at all times;
(b)undertake any clearance and/or maintenance required within reasonable timescales;
(c)provide ScottishPower Renewables with copies of keys required to unlock any lockable bollards or similar that would prevent or hinder the use of the over-run areas; and
(d)restrict access to those parts of the over-run areas where lockable bollards or similar are in place to the undertaker, the local highway authority and to ScottishPower Renewables only.
(2) In the event that the existing re-aligned A30 is adopted the undertaker will use reasonable endeavours to procure that the local highway authority complies with the obligations under paragraph (1).
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: