5.—(1) The authorised development must be carried out in accordance with the code of construction practice.
(2) No part of the authorised development may be commenced until the following plans and strategies, required by the code of construction practice, have been prepared for that part of the authorised development—
(a)Construction Site River Strategy: to be prepared in consultation with the relevant planning authority and the PLA;
(b)Emergency Plan: to be prepared in consultation with the local emergency services and the relevant planning authority;
(c)Fire Plan: to be prepared in consultation with the London Fire and Emergency Planning Authority;
(d)Lighting Management Plan: to be prepared in consultation with the relevant planning authority, the PLA and the Environment Agency; and
(e)Site Waste Management Plan: to be prepared in consultation with the relevant planning authority and the Environment Agency.
(3) No part of the authorised development may be commenced until the following plans and strategies, required by the code of construction practice, have been prepared for that part of the authorised development and approved by the relevant planning authority, the Environment Agency or the PLA (as the case may be)—
(a)Air Quality Management Plan: to be approved by the relevant planning authority including in the London Borough of Newham, such scheme of ventilation at the Hoola building as necessary to reduce the exposure of first floor residential accommodation to nitrogen oxide to acceptable levels;
(b)Archaeological Written Scheme of Investigation: to be prepared in consultation with Historic England and, in respect of any elements within the river Thames, the PLA and the MMO, and approved by the relevant planning authority;
(c)Community Engagement Plan: to be approved by the relevant planning authority;
(d)Construction Materials Management Plan incorporating commitments to river transport: to be approved by the relevant planning authority;
(e)Construction Traffic Management Plan: to be approved by the relevant planning authority, in consultation with the relevant highway authority;
(f)Ecology Management Plan: to be prepared in consultation with Natural England and approved by the relevant planning authority;
(g)Flood Warning and Evacuation Plan (which forms part of the Emergency Plan to be prepared under sub-paragraph (2)(b)): to be approved by the relevant planning authority, in consultation with the Environment Agency;
(h)Groundwater Monitoring and Verification Plan: to be approved by the Environment Agency;
(i)Noise and Vibration Management Plan: to be approved by the relevant planning authority;
(j)Passage Plan: to be approved by the PLA; and
(k)Construction Environmental Management Plan: to be approved in consultation with the relevant planning authority and the PLA
(4) The relevant highway authority for the purposes of sub-paragraph (3)(e) is each highway authority for the highways affected by the Construction Traffic Management Plan.
(5) The authorised development must be carried out in accordance with the plans and strategies prepared or approved under sub-paragraphs (2) and (3).
(6) TfL must make the plans and strategies prepared or approved under sub-paragraphs (2) and (3) available in an electronic form suitable for inspection by members of the public until the authorised development has been opened for public use.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: