Search Legislation

The Measuring Instruments Regulations 2016

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: SCHEDULE 1D

 Help about opening options

Alternative versions:

Status:

Point in time view as at 31/12/2020.

Changes to legislation:

There are currently no known outstanding effects for the The Measuring Instruments Regulations 2016, SCHEDULE 1D. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Regulations 2 and 39(1)

[F1SCHEDULE 1DE+W+SGAS METERS (MI-002) (Annex IV to the Directive)

This schedule has no associated Explanatory Memorandum

The relevant requirements of Schedule 1A, the specific requirements of this Schedule and the conformity assessment procedures listed in this Schedule, apply to gas meters.

DEFINITIONS

Minimum flowrate (Qmin)The lowest flowrate at which the gas meter provides indications that satisfy the requirements regarding maximum permissible error (MPE).
Maximum flowrate (Qmax)The highest flowrate at which the gas meter provides indications that satisfy the requirements regarding MPE.
Transitional flowrate (Qt)The transitional flowrate is the flowrate occurring between the maximum and minimum flowrates at which the flowrate range is divided into two zones, the ‘upper zone’ and the ‘lower zone’. Each zone has a characteristic MPE.
Overload Flowrate (Qr)The overload flowrate is the highest flowrate at which the meter operates for a short period of time without deteriorating.
Base conditionsThe specified conditions to which the measured quantity of fluid is converted.

PART IE+W+SSPECIFIC REQUIREMENTS

GAS METERS

1.  Rated operating conditionsE+W+S

The manufacturer shall specify the rated operating conditions of the gas meter, taking into account:

1.1.  The flowrate range of the gas shall fulfil at least the following conditions:E+W+S

ClassQmax/QminQmax/QtQr/Qmax
1.5 150 101.2
1.0 20 51.2

1.2.  The temperature range of the gas, with a minimum range of 40 °C.E+W+S

The fuel/gas related conditionsE+W+S

1.3.  The gas meter shall be designed for the range of gases and supply pressures of the United Kingdom. In particular the manufacturer shall indicate:

  • — the gas family or group;

  • — the maximum operating pressure.

1.4.  A minimum temperature range of 50 °C for the climatic environment.E+W+S

1.5.  The nominal value of the AC voltage supply and/or the limits of DC supply.E+W+S

Maximum permissible error (MPEs)E+W+S

Gas meter indicating the volume at metering conditions or massE+W+S

Table 1
Class1.51.0
Qmin ≤ Q < Qt3 %2 %
Qt ≤ Q ≤ Qmax1.5 %1 %

The gas meter shall not exploit the MPEs or systematically favour any party.

2.2.  For a gas meter with temperature conversion, which only indicates the converted volume, the MPE of the meter is increased by 0.5 % in a range of 30 °C extending symmetrically around the temperature specified by the manufacturer that lies between 15 °C and 25 °C. Outside this range, an additional increase of 0.5 % is permitted in each interval of 10 °C.E+W+S

Permissible effect of disturbancesE+W+S

Electromagnetic immunityE+W+S

3.1.1.  The effect of an electromagnetic disturbance on a gas meter shall be such that:E+W+S

  • — the change in the measurement result is no greater than the critical change value as defined in paragraph 3.1.3, or

  • — the indication of the measurement result is such that it cannot be interpreted as a valid result, such as a momentary variation that cannot be interpreted, memorised or transmitted as a measuring result.

3.1.2.  After undergoing a disturbance, the gas meter shall:E+W+S

  • — recover to operate within MPE, and

  • — have all measurement functions safeguarded, and

  • — allow recovery of all measurement data present just before the disturbance.

3.1.3.  The critical change value is the smaller of the two following values:E+W+S

  • — the quantity corresponding to half of the magnitude of the MPE in the upper zone on the measured volume;

  • — the quantity corresponding to the MPE on the quantity corresponding to one minute at maximum flowrate.

Effect of upstream-downstream flow disturbancesE+W+S

3.2.  Under installation conditions specified by the manufacturer, the effect of the flow disturbances shall not exceed one third of the MPE.

DurabilityE+W+S

4.  After an appropriate test, taking into account the period of time estimated by the manufacturer, has been performed, the following criteria shall be satisfied:

Class 1.5 Gas MetersE+W+S

4.1.1.  The variation of the measurement result after the durability test when compared with the initial measurement result for the flow rates in the range Qt to Qmax shall not exceed the measurement result by more than 2 %.E+W+S

4.1.2.  The error of indication after the durability test shall not exceed twice the MPE in paragraph 2.E+W+S

Class 1.0 Gas MetersE+W+S

4.2.1.  The variation of the measurement result after the durability test when compared with the initial measurement result shall not exceed one-third of the MPE in paragraph 2.E+W+S

4.2.2.  The error of indication after the durability test shall not exceed the MPE in paragraph 2.E+W+S

SuitabilityE+W+S

5.1.  A gas meter powered from the mains (AC or DC) shall be provided with an emergency power supply device or other means to ensure, during a failure of the principal power source, that all measuring functions are safeguarded.E+W+S

5.2.  A dedicated power source shall have a lifetime of at least five years. After 90 % of its lifetime an appropriate warning shall be shown.E+W+S

5.3.  An indicating device shall have a sufficient number of digits to ensure that the quantity passed during 8,000 hours at Qmax does not return the digits to their initial values.E+W+S

5.4.  The gas meter shall be able to be installed to operate in any position declared by the manufacturer in its installation instruction.E+W+S

5.5.  The gas meter shall have a test element, which shall enable tests to be carried out in a reasonable time.E+W+S

5.6.  The gas meter shall respect the MPE in any flow direction or only in one flow direction clearly marked.E+W+S

UnitsE+W+S

6.  Metered quantity shall be displayed in cubic metre, or in kilogram.

PART IIE+W+SPUTTING INTO USE AND CONFORMITY ASSESSMENT

7.  Putting into useE+W+S

(a)The measurement of residential use must be performed by means of any Class 1.5 gas meter, or by Class 1.0 gas meters which have a Qmax/Qmin ratio equal to or greater than 150.

(b)Measurement of commercial and/or light industrial use must be performed by any Class 1.0 or Class 1.5 gas meter.

(c)The person responsible for installing a gas meter must have regard to the requirements under paragraphs 1.2 and 1.3 of Part I of this Schedule and must ensure that the gas meter is appropriate for the accurate measurement of consumption that is foreseen or foreseeable.

CONFORMITY ASSESSMENT The conformity assessment procedures specified in the modules in Schedule 1B applicable to gas meters that the manufacturer can choose between are:

(a)B and F;

(b)B and D; or

(c)H1.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources