Print Options
PrintThe Whole
Instrument
PrintThe Whole
Schedule
PrintThe Whole
Part
PrintThe Whole
Cross Heading
PrintThis
Section
only
Changes over time for: Paragraph V


Timeline of Changes
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Status:
Point in time view as at 06/04/2018.
Changes to legislation:
There are currently no known outstanding effects for The Town and Country Planning (General Permitted Development) (England) Order 2015, Paragraph V.

Changes to Legislation
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
Development not permittedE+W
This section has no associated Explanatory Memorandum
V.1 Development is not permitted by Class V if—
(a)the application for planning permission referred to was made before 5th December 1988;
(b)it would be carried out more than 10 years after the grant of planning permission;
(c)the development would consist of a change of use of a building to use as betting office or pay day loan shop; or
(d)it would result in the breach of any condition, limitation or specification contained in that planning permission in relation to the use in question.