Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
H. The deposit, on premises used as a mine or on ancillary mining land already used for the purpose, of waste derived from the winning and working of minerals at that mine or from minerals brought to the surface at that mine, or from the treatment or the preparation for sale, consumption or utilization of minerals from the mine.
H.1 Development is not permitted by Class H if—
(a)in the case of waste deposited in an excavation, waste would be deposited at a height above the level of the land adjoining the excavation, unless that is provided for in a waste management scheme or a relevant scheme; or
(b)in any other case, the superficial area or height of the deposit (measured as at 21st October 1988) would be increased by more than 10%, unless such an increase is provided for in a waste management scheme or in a relevant scheme.
H.2 Development is permitted by Class H subject to the following conditions—
(a)except in a case where a relevant scheme or a waste management scheme has already been approved by the mineral planning authority M1, the developer must, if the mineral planning authority so require, within 3 months or such longer period as the authority may specify, submit a waste management scheme for that authority's approval; and
(b)where a waste management scheme or a relevant scheme has been approved, the depositing of waste and all other activities in relation to that deposit is carried out in accordance with the scheme as approved.
Marginal Citations
M1See section 1(4) of the Act.
H.3 For the purposes of Class H—
“ancillary mining land” means land adjacent to and occupied together with a mine at which the winning and working of minerals is carried out in pursuance of planning permission granted or deemed to be granted under Part 3 of the Act (control over development) M2; and
“waste management scheme” means a scheme required by the mineral planning authority to be submitted for their approval in accordance with the condition in paragraph H.2(a) which makes provision for—
the manner in which the depositing of waste (other than waste deposited on a site for use for filling any mineral excavation in the mine or on ancillary mining land in order to comply with the terms of any planning permission granted on an application or deemed to be granted under Part 3 of the Act) is to be carried out after the date of the approval of that scheme;
where appropriate, the stripping and storage of the subsoil and topsoil;
the restoration and aftercare of the site.
Marginal Citations
M2See in particular section 58; which was amended by Schedule 12 to the Localism Act 2011 (c. 20) and Schedule 1 to the Growth and Infrastructure Act 2013 (c. 27).
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: