PART 15FOR THE PROTECTION OF THE OIL AND PIPELINES AGENCY

119.—(1) Unless agreed otherwise in writing between the undertaker and the Oil and Pipelines Agency, the provisions of this Part of this Schedule will apply.

(2) This paragraph applies if any part of the river at, or adjacent to, the Oil and Pipelines Agency’s facility on the river becomes subject to sedimentation, scouring, currents or wave action which—

(a)is, during the period beginning with the commencement of the construction of a tidal work and ending with the expiration of 10 years after the date on which all the tidal works constructed under this Order are completed, wholly or partly caused by a tidal work; and

(b)for the safety of navigation or for the protection of the Oil and Pipelines Agency’s facility on the river, should in the reasonable opinion of the Oil and Pipelines Agency be prevented, mitigated or made good.

(3) The undertaker must either—

(a)pay to the Oil and Pipelines Agency any additional expense to which the Oil and Pipelines Agency may reasonably be put in preventing, mitigating or making good the sedimentation, scouring, currents or wave action so far as required by the needs of traffic in, or the flow or regime of, the river at, or adjacent to, the Oil and Pipelines Agency’s facility so far as (in any case) it is attributable to the tidal work; or

(b)carry out the necessary dredging at its own expense and subject to the prior approval of the Oil and Pipelines Agency, such prior approval not to be unreasonably withheld or delayed,

and the reasonable expenses payable by the undertaker under this paragraph include any additional expenses accrued or incurred by the Oil and Pipelines Agency in carrying out surveys or studies in connection with the implementation of this paragraph.

120.  Before extinguishing any existing rights for the Oil and Pipelines Agency to pass along parcel 03009 (Station Road), the undertaker must, with the agreement of the Oil and Pipelines Agency, create a new right of way for the Oil and Pipelines Agency, such agreement not to be unreasonably withheld or delayed, and to be subject to arbitration under article 57 (arbitration).

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources