Search Legislation

The Able Marine Energy Park Development Consent Order 2014

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)

Status:

This is the original version (as it was originally made). This item of legislation is currently only available in its original format.

This section has no associated Explanatory Memorandum

17.—(1) The Harbour Authority is responsible for and must make good to the Conservancy Authority all reasonable financial costs or losses not otherwise provided for in this Part of this Schedule which may reasonably be incurred or suffered by the Conservancy Authority by reason of—

(a)the construction or operation of the authorised works or the failure of the authorised works;

(b)anything done in relation to a mooring or buoy under paragraph 9; or;

(c)any act or omission of the Harbour Authority, its employees, contractors or agents or others whilst engaged upon the construction or operation of the authorised works or dealing with any failure of the authorised works,

and the Harbour Authority must indemnify the Conservancy Authority from and against all claims and demands arising out of or in connection with the authorised works or any such failure, act or omission.

(2) The fact that any act or thing may have been done—

(a)by the Conservancy Authority on behalf of the Harbour Authority; or

(b)by the Harbour Authority, its employees, contractors or agents in accordance with plans or particulars submitted to or modifications or conditions specified by the Conservancy Authority, or in a manner approved by the Conservancy Authority, or under its supervision or the supervision of its duly authorised representative,

does not (if it was done or required without negligence on the part of the Conservancy Authority or its duly authorised representative, employee, contractor or agent) excuse the Harbour Authority from liability under the provisions of this paragraph.

(3) The Conservancy Authority must give the Harbour Authority reasonable notice of any such claim or demand as is referred to in sub-paragraph (1), and no settlement or compromise of any such claim or demand is to be made without the prior consent of the Harbour Authority.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources