The operational costs levy

This section has no associated Explanatory Memorandum

23.—(1) An electricity supplier must make a payment (“an operational cost payment”) to the CFD counterparty for each day that supplier makes an electricity supply during an operational cost period.

(2) The amount of an operational cost payment to be paid by a supplier in respect of a day is equal to the amount of electricity supplied by that supplier on that day multiplied by the operational levy rate.

(3) The CFD counterparty must, as soon as reasonably practicable after the BSCCo has carried out an Initial Volume Allocation Run in respect of a day in an operational cost period, issue a notice to each electricity supplier who supplied electricity on that day stating the operational cost payment which the supplier to whom the notice is issued must pay in respect of that day.

(4) An electricity supplier must make an operational cost payment in respect of a day by the operational cost payment date in relation to that payment.

(5) The operational cost payment date in relation to an operational cost payment is—

(a)in relation to an operational cost payment due in respect of any day in the first operational cost period, the 5th working day after the CFD counterparty has issued a notice under paragraph (3) to the supplier who must make that payment in respect of every operational cost payment due from that supplier in respect of that period;

(b)in relation to an operational cost payment due in respect of a day in any other operational cost period, the 5th working day after the day on which the CFD counterparty has issued a notice under paragraph (3) to the supplier who must make that payment.

(6) Where an electricity supplier fails to make an operational cost payment by the operational cost payment date in relation to that payment, that supplier must pay the CFD counterparty simple interest on any unpaid amount at the rate specified in regulation 35(1) from the day after the operational cost payment date.

(7) For the purposes of this regulation—

(a)the operational levy rate is £0.079 per megawatt hour; and

(b)the amount of electricity supplied by an electricity supplier on a particular day is the amount of electricity which the BSCCo determines, on the basis of an Initial Volume Allocation Run carried out in relation to that day, as the amount of electricity which that supplier supplied on that day.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources