7.—(1) Subject to regulation 8, this regulation applies where—
(a)a building is to be sold or rented out; and
(b)no valid energy performance certificate is available for that building.
(2) Before the building is put on the market, the relevant person must secure that an energy performance certificate is commissioned for the building.
(3) Before marketing the building, a person acting on behalf of the relevant person must be satisfied that an energy performance certificate has been commissioned for the building.
(4) The relevant person and a person acting on behalf of the relevant person must use all reasonable efforts to secure that a valid energy performance certificate is obtained for the building before the end of a period of 7 days starting with the day on which the building was first put on the market.
(5) Where any person subject to the duty in paragraph (4) is unable, despite using all reasonable efforts, to secure that a valid energy performance certificate is obtained for the building before the end of the 7 day period specified in that paragraph, the person shall secure that the certificate is obtained before the end of the period of 21 days immediately following the 7 day period.
(6) In this regulation—
(a)“the market” means the property market in England and Wales;
(b)a building is put on the market when the fact that it is or may become available for sale or rent is, with the intention of marketing the building, first made public in England and Wales by or on behalf of the relevant person;
(c)a fact is made public when it is advertised or otherwise communicated (in whatever form and by whatever means) to the public or to a section of the public;
(d)an energy performance certificate is commissioned when a request is made—
(i)which is properly addressed to an energy assessor who is accredited to produce energy performance certificates for the category of building in question, and
(ii)which is in such form, contains all such information and is accompanied by such payment or undertaking to make such payment as is usually necessary to obtain a certificate.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: