Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.
Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):
11D.—(1) Where there is more than one contractor, or it is reasonably foreseeable that more than one contractor will be working on a project, the client must appoint in writing—
(a)a designer with control over the design work as the principal designer for the purposes of these Regulations, and
(b)a contractor with control over the building work as the principal contractor for the purposes of these Regulations.
(2) A client is treated as complying with the requirement in paragraph (1) if, instead of appointing a person for the purposes of these Regulations, they certify, in writing, that the person who is the CDM principal designer, or, as the case may be, the CDM principal contractor, is treated as appointed as the principal designer or, as the case may be, the principal contractor, for the purposes of these Regulations.
(3) The appointments under this regulation must be made—
(a)in relation to a project which includes higher-risk building work for which an application for building control approval must be submitted to the regulator, before that application is submitted;
(b)in relation to any other project, before the construction phase begins.
(4) Where the appointment of a principal designer or the principal contractor ends before the end of the project, as soon as reasonably practicable the client must appoint a new principal designer or new principal contractor, as the case may be, under this regulation.
(5) Where the client fails to appoint a principal designer (or a replacement principal designer) or, as the case may be, a principal contractor (or a replacement principal contractor), the client must fulfil the duties of the principal designer or the principal contractor, as the case may be, under these Regulations until they appoint another person to that role.
(6) Where there is only one contractor working on a project that contractor is to be treated as appointed as the principal contractor and must fulfil the duties of the principal contractor set out in these Regulations.
(7) Where paragraph (6) applies and—
(a)there is only one designer, or it is reasonably foreseeable that there will be only one designer working on a project, that designer must fulfil the duties of the principal designer set out in these Regulations; or
(b)there is more than one designer or it is reasonably foreseeable that there will be more than one designer working on a project at any time—
(i)the designers must agree in writing which designer is to fulfil the duties of the principal designer set out in these Regulations (“the lead designer”);
(ii)the lead designer must give a copy of the agreement to the client.
(8) In relation to higher-risk building work, on appointing a principal designer, for each appointment the client must keep a record, in writing, of the steps it took under paragraph (2) to (4) of regulation 11E (considerations before a person carries out work).
(9) In relation to higher-risk building work, on appointing a principal contractor, for each appointment the client must keep a record, in writing, of the steps it took under paragraphs (2), (3) and (5) of regulation 11E (considerations before a person carries out work).
(10) In relation to higher-risk building work, on appointing any other person, the person making the appointment must give to the client (and the client must keep) a record, in writing, of the steps the person making the appointment took under regulation 11E(2) (considerations before a person carries out work).]
Textual Amendments
F1Pt. 2A inserted (E.) (1.10.2023) by The Building Regulations etc. (Amendment) (England) Regulations 2023 (S.I. 2023/911), regs. 1(2), 6(1) (with regs. 22-24)
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:
This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: