Amendment of article 12 (approval of actions by the Authority)

This section has no associated Explanatory Memorandum

12.—(1) Article 12 (approval of actions by the Authority) is amended as follows.

(2) For paragraph (1) substitute—

(1) The Authority must determine whether or not it approves an action as a qualifying action and whether that approval is in respect of a supplier’s—

(a)insulation obligation;

(b)priority group obligation; or

(c)super priority group obligation..

(3) For paragraph (6) substitute—

(6) The benchmark action means an action under the 2001 Order or the 2004 Order, as applicable, which achieved the greatest carbon emission reductions for an action of that type..

(4) In paragraph (7B)(a) after “requests” insert “, in writing,”.

(5) In paragraph (7B)(b) after “requested” insert “, in writing,”.

(6) For paragraph (7C) substitute—

(7C) The Authority must not on or after 1st April 2011 approve as a qualifying action the provision of compact fluorescent lamps or halogen lamps..

(7) After paragraph (7C) insert—

(7D)  The Authority must not on or after 1st August 2010 approve as a qualifying action the provision of a measure which will not be professionally installed unless that measure has been requested, in writing, by a domestic energy user.

(7E) The Authority must not on or after 1st April 2011 approve as a qualifying action the provision of—

(a)an air source heat pump;

(b)a biomass boiler with a capacity of 300 kW or less;

(c)a combined heat and power plant with an electrical capacity of 2 kW or less;

(d)a ground source heat pump;

(e)a hydro generating station with a capacity of 50 kW or less;

(f)a solar photovoltaic panel with a capacity of 50 kW or less;

(g)a solar thermal water heating system with a capacity of 300 kW or less; or

(h)wind turbine with a capacity of 50 kW or less,

unless it is satisfied that the measure will be promoted to a member of the super priority group..

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Memorandum

Explanatory Memorandum sets out a brief statement of the purpose of a Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Statutory Instrument accessible to readers who are not legally qualified and accompany any Statutory Instrument or Draft Statutory Instrument laid before Parliament from June 2004 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources