3.—(1) Prior to commencing a transitional tender exercise in relation to a qualifying project, the Authority shall calculate the economic and efficient costs which ought to be, or ought to have been, incurred in connection with developing and constructing the transmission assets, based on all relevant information available to the Authority, in accordance with paragraph (2).
(2) The calculation of costs in paragraph (1) shall be–
(a)where the construction of the transmission assets has not reached the stage when those transmission assets are available for use for the transmission of electricity, an estimate of the costs which ought to be incurred in connection with the development and construction of those transmission assets, or
(b)where the construction of the transmission assets has reached the stage when those transmission assets are available for use for the transmission of electricity, an assessment of the costs which ought to have been incurred in connection with the development and construction of those transmission assets.
(3) Where the Authority–
(a)has previously estimated the costs in accordance with paragraph (2)(a); and
(b)is satisfied with the evidence provided by the developer that those transmission assets are available for use for the transmission of electricity,
the Authority shall, as soon as reasonably practicable, assess the costs which ought to have been incurred in connection with the development and construction of those transmission assets.
(4) The developer shall provide such further information to the Authority as the Authority reasonably requires to enable it to estimate, in accordance with paragraph (2)(a), or assess, in accordance with paragraph (2)(b) or (3), the costs which ought to be, or ought to have been, incurred in connection with the development and construction of those transmission assets.
4.—(1) Where the Authority has estimated the costs in accordance with regulation 3(2)(a), it shall, as soon as reasonably practicable, give notice to the developer to make a payment to the Authority of a sum determined in accordance with the Authority’s cost recovery methodology in relation to estimating those costs.
(2) Where the Authority has assessed the costs in accordance with regulation 3(2)(b) or 3(3), it shall, as soon as reasonably practicable after the transitional tender exercise has been held in accordance with these Regulations, give notice to the successful bidder to make a payment to the Authority of a sum determined in accordance with the Authority’s cost recovery methodology in relation to assessing those costs.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: