Rule 22—(1) An application to the Court of Appeal for permission to appeal from a value added tax tribunal direct to that Court under section 26 of the Finance Act 1985(1) shall be made within 28 days from the date on which the tribunal certifies that its decision involves a point of law relating wholly or mainly to the construction of an enactment or of a statutory instrument, or of any of the Community Treaties or any Community Instrument, which has been fully argued before it and fully considered by it.
(2) Such an application shall be made by the parties jointly by filing a copy of the decision, endorsed with the certificate of the tribunal and a statement of the grounds of the application, with the court, and shall be determined by a single judge of the Court of Appeal, who may do so without a hearing.
(3) In the case of all applications, the Court shall notify the parties of the determination of the single judge, and
(a)where permission to appeal to the Court of Appeal is granted, the appellant shall within 14 days after such notification serve the notice of appeal on the chairman of the tribunal as well as on the party or parties required to be served by rule 3;
(b)where permission to appeal to the Court of Appeal is refused, the period specified in Order 55, rule 4 (2) for appealing to the High Court shall be calculated from the date of notification of the refusal.
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Schedule you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: