Search Legislation

The Civil Procedure Rules 1998

 Help about what version

What Version

  • Latest available (Revised)
  • Original (As made)
 Help about advanced features

Advanced Features

More Resources

Changes to legislation:

There are currently no known outstanding effects for the The Civil Procedure Rules 1998, Cross Heading: SECTION II. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

[F1SECTION IIE+WCosts Payable by one Party to another – Commencement of Detailed Assessment Proceedings

Textual Amendments

Application of this SectionE+W

47.5.  This Section of Part 47 applies where a cost officer is to make a detailed assessment of—

(a)costs which are payable by one party to another; or

(b)the sum which is payable by one party to the prescribed charity pursuant to an order under section 194(3) of the 2007 Act.

Commencement of detailed assessment proceedingsE+W

47.6.(1) Detailed assessment proceedings are commenced by the receiving party serving on the paying party—

(a)notice of commencement in the relevant practice form; F2...

(b)[F3a copy or copies of the bill of costs, as required by Practice Direction 47; and]

(c)[F4if required by Practice Direction 47,] a breakdown of the costs claimed for each phase of the proceedings

(Rule 47.7 sets out the period for commencing detailed assessment proceedings.)

(2) The receiving party must also serve a copy of the notice of commencement [F5, the bill and, [F6if required by Practice Direction 47,] the breakdown] on any other relevant persons specified in Practice Direction 47.

(3) A person on whom a copy of the notice of commencement is served under paragraph (2) is a party to the detailed assessment proceedings (in addition to the paying party and the receiving party).

( Practice Direction 47 deals with—

  • other documents which the party must file when requesting detailed assessment;

  • the court’s powers where it considers that a hearing may be necessary;

  • the form of a bill; and

  • the length of notice which will be given if a hearing date is fixed.)

[F7(Paragraphs 7B.2 to 7B.7 of the Practice Direction - Civil Recovery Proceedings contain provisions about detailed assessment of costs in relation to civil recovery orders.)]

Period for commencing detailed assessment proceedingsE+W

47.7.  The following table shows the period for commencing detailed assessment proceedings.

Source of right to detailed assessmentTime by which detailed assessment proceedings must be commenced
Judgment, direction, order, award or other determination3 months after the date of the judgment etc. Where detailed assessment is stayed pending an appeal, 3 months after the date of the order lifting the stay
Discontinuance under Part 383 months after the date of service of notice of discontinuance under rule 38.3; or 3 months after the date of the dismissal of application to set the notice of discontinuance aside under rule 38.4
Acceptance of an offer to settle under Part 363 months after the date when the right to costs arose

Sanction for delay in commencing detailed assessment proceedingsE+W

47.8.(1) Where the receiving party fails to commence detailed assessment proceedings within the period specified—

(a)in rule 47.7; or

(b)by any direction of the court,

the paying party may apply for an order requiring the receiving party to commence detailed assessment proceedings within such time as the court may specify.

(2) On an application under paragraph (1), the court may direct that, unless the receiving party commences detailed assessment proceedings within the time specified by the court, all or part of the costs to which the receiving party would otherwise be entitled will be disallowed.

(3) If—

(a)the paying party has not made an application in accordance with paragraph (1); and

(b)the receiving party commences the proceedings later than the period specified in rule 47.7,

the court may disallow all or part of the interest otherwise payable to the receiving party under—

(i)section 17 of the Judgments Act 1838; or

(ii)section 74 of the County Courts Act 1984,

but will not impose any other sanction except in accordance with rule 44.11 (powers in relation to misconduct).

(4) Where the costs to be assessed in a detailed assessment are payable out of the Community Legal Service Fund, this rule applies as if the receiving party were the solicitor to whom the costs are payable and the paying party were the Legal Services Commission.

[F8(5) Where the costs to be assessed in a detailed assessment are payable by the Lord Chancellor under Part 1 of the Legal Aid, Sentencing and Punishment of Offenders Act 2012, this rule applies as if the receiving party were the solicitor to whom the costs are payable and the paying party were the Lord Chancellor.]

Points of dispute and consequence of not servingE+W

47.9.(1) The paying party and any other party to the detailed assessment proceedings may dispute any item in the bill of costs by serving points of dispute on—

(a)the receiving party; and

(b)every other party to the detailed assessment proceedings.

(2) The period for serving points of dispute is 21 days after the date of service of the notice of commencement.

(3) If a party serves points of dispute after the period set out in paragraph (2), that party may not be heard further in the detailed assessment proceedings unless the court gives permission.

(Practice Direction 47 sets out requirements about the form of points of dispute.)

(4) The receiving party may file a request for a default costs certificate if—

(a)the period set out in paragraph (2) for serving points of dispute has expired; and

(b)the receiving party has not been served with any points of dispute.

(5) If any party (including the paying party) serves points of dispute before the issue of a default costs certificate the court may not issue the default costs certificate.

(Section IV of this Part sets out the procedure to be followed after points of dispute have been served.)

Procedure where costs are agreedE+W

47.10.(1) If the paying party and the receiving party agree the amount of costs, either party may apply for a costs certificate (either interim or final) in the amount agreed.

(Rule 47.16 and rule 47.17 contain further provisions about interim and final costs certificates respectively)

(2) An application for a certificate under paragraph (1) must be made to the court which would be the venue for detailed assessment proceedings under rule 47.4.]

Back to top

Options/Help

Print Options

You have chosen to open The Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument as a PDF

The Whole Instrument you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Instrument without Schedules as a PDF

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Instrument

The Whole Instrument you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Instrument without Schedules

The Whole Instrument without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.