14.—(1) Before the design of a well is commenced the well-operator shall cause—
(a)the geological strata and formations, and fluids within them, through which it may pass; and
(b)any hazards which such strata and formations may contain,
to be assessed.
(2) The well-operator shall ensure that account is taken of the assessment required by paragraph (1) when the well is being designed and constructed.
(3) The well-operator shall ensure that, while an operation (including the drilling of the well) is carried out in relation to the well, those matters described in sub-paragraphs (a) and (b) of paragraph (1) shall, so far as is reasonably practicable, be kept under review and that, if any change is observed in those matters, such modification is made, where appropriate, to—
(a)the design and construction of the well; or
(b)any procedures,
as are necessary to ensure that the purposes described in regulation 13(1) will continue to be fulfilled.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include: