The Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

Changes over time for: PART IV

 Help about opening options

Version Superseded: 19/07/2015

Alternative versions:

Status:

Point in time view as at 21/02/1998.

Changes to legislation:

There are currently no known outstanding effects for the The Offshore Installations and Wells (Design and Construction, etc.) Regulations 1996, PART IV. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

PART IVE+W+S WELLS

General dutyE+W+S

13.—(1) The well-operator shall ensure that a well is so designed, modified, commissioned, constructed, equipped, operated, maintained, suspended and abandoned that—

(a)so far as is reasonably practicable, there can be no unplanned escape of fluids from the well; and

(b)risks to the health and safety of persons from it or anything in it, or in strata to which it is connected, are as low as is reasonably practicable.

(2) The provisions of regulations 14 to 19 and 21 are without prejudice to the generality of the requirements of paragraph (1) save that, where regulation 17(2) places a duty on the duty holder for an installation, the well-operator is not under the same duty.

Assessment of conditions below groundE+W+S

14.—(1) Before the design of a well is commenced the well-operator shall cause—

(a)the geological strata and formations, and fluids within them, through which it may pass; and

(b)any hazards which such strata and formations may contain,

to be assessed.

(2) The well-operator shall ensure that account is taken of the assessment required by paragraph (1) when the well is being designed and constructed.

(3) The well-operator shall ensure that, while an operation (including the drilling of the well) is carried out in relation to the well, those matters described in sub-paragraphs (a) and (b) of paragraph (1) shall, so far as is reasonably practicable, be kept under review and that, if any change is observed in those matters, such modification is made, where appropriate, to—

(a)the design and construction of the well; or

(b)any procedures,

as are necessary to ensure that the purposes described in regulation 13(1) will continue to be fulfilled.

Design with a view to suspension and abandonmentE+W+S

15.  The well-operator shall ensure that a well is so designed and constructed that, so far as is reasonably practicable—

(a)it can be suspended or abandoned in a safe manner; and

(b)after its suspension or abandonment there can be no unplanned escape of fluids from it or from the reservoir to which it led.

MaterialsE+W+S

16.  The well-operator shall ensure that every part of a well is composed of material which is suitable for achieving the purposes described in regulation 13(1).

Well controlE+W+S

17.—(1) Before an operation in relation to a well (including the drilling of a well) is begun elsewhere than at a borehole site to which the Borehole Sites and Operations Regulations 1995 M1 apply, the well-operator shall ensure that suitable well control equipment is provided for use during such operations to protect against blowouts.

(2) In the case of an operation to which paragraph (1) applies which is begun—

(a)from an installation, the duty holder; and

(b)otherwise than from an installation, the well-operator,

shall ensure that equipment provided pursuant to paragraph (1) is deployed when the prevailing well and operational conditions so require.

Marginal Citations

Arrangements for examinationE+W+S

18.—(1) Before the design of a well is commenced or adopted the well-operator shall make and put into effect arrangements relating to the well of a kind described in paragraph (2) or (where such arrangements already have effect in relation to another well) apply such arrangements, with any appropriate modifications, to the well.

(2) The arrangements referred to in paragraph (1) are arrangements in writing for such examinations, by independent and competent persons, of any part of the well, or similar well, information, or work in progress, and the making of such reports and recommendations, as are suitable for ensuring (with the assistance of such other measures as the well-operator takes) that the well is so designed and constructed, and is maintained in such repair and condition, that—

(a)so far as is reasonably practicable, there can be no unplanned escape of fluids from the well; and

(b)risks to the health and safety of persons from it or anything in it, or in strata to which it is connected, are as low as is reasonably practicable.

(3) The well-operator shall review and revise the arrangements as often as may be appropriate.

(4) The well-operator shall ensure that the arrangements, any revision of them, and reports and recommendations pursuant to them are kept at an address in Great Britain notified to the Executive, until the expiration of six months after the arrangements and any revision of them cease to be current.

(5) In the case of a well which, at the coming into force of these Regulations, is completed, the well-operator shall make and put into effect or (as the case may be) apply the arrangements described in paragraph (1) within 1 year after such coming into force.

(6) In the case of a well, the design of which was commenced or adopted before the coming into force of these Regulations, but which is not, at such coming into force, completed, the well-operator shall make and put into effect or (as the case may be) apply the arrangements described in paragraph (1)—

(a)forthwith; or

(b)within 1 year after such coming into force, in a case where a well consent was given not more than 1 year before such coming into force.

(7) For the purpose of this regulation a person shall be regarded as independent only where—

(a)his examination will not involve the consideration by him of an aspect, of a thing liable to be examined, for which he bears or has borne such responsibility as might compromise his objectivity; and

(b)he will be sufficiently independent of a management system, or of a part thereof, which bears or has borne any responsibility for an aspect, which he might consider, of a thing liable to be examined, to ensure that he will be objective in discharging his function.

(8) In this regulation “well consent" means a consent in writing of the Secretary of State for Trade and Industry to the commencement of drilling of the well required by paragraph (1) of—

(a)clause 19 of the model clauses contained in Schedule 4 to the Petroleum (Production) (Seaward Areas) Regulations 1988 M2;

(b)clause 15 of the model clauses contained in Schedule 6 to the Petroleum (Production) (Landward Areas) Regulations 1991 M3;;

(c)clause 17 of the model clauses contained in Schedule 3 to the Petroleum (Production) (Landward Areas) Regulations 1995 M4,

in a case where the clause is, pursuant to the relevant Regulations, incorporated in a licence.

Marginal Citations

M2S.I. 1988/1213, to which there are amendments not relevant to these Regulations.

Provision of drilling etc. informationE+W+S

19.—(1) Where an operation to which this paragraph applies is being carried out on a well the well-operator shall cause to be sent to the Executive, at such intervals as may be agreed or, failing agreement, at intervals of one week calculated from its commencement, a report comprising the following information—

(a)the identifying number, and any slot number, of the well;

(b)the name of any installation or vessel involved;

(c)a summary of the activity in the course of the operation since its commencement, or the previous report;

(d)the diameter and true vertical and measured depths of—

(i)any hole drilled; and

(ii)any casing installed;

(e)the drilling fluid density immediately before making the report; and

(f)in the case of an existing well, its current operational state.

(2) Paragraph (1) applies to—

(a)a drilling operation;

(b)a workover operation;

(c)an abandonment operation;

(d)an operation consisting in the completion of a well;

(e)any other operation of a kind involving substantial risk of the unplanned escape of fluids from a well.

Co-operationE+W+S

20.  Every person who is, or is to be concerned (in whatever capacity) in an operation in relation to a well (including the drilling of a well) shall co-operate with the well-operator so far as is necessary to enable him to discharge his duties under regulations 13(1) and 17.

Information, instruction, training and supervisionE+W+S

21.  In the case of a drilling, well intervention or workover operation to be carried out on a well—

(a)from an installation, the duty holder; and

(b)otherwise than from an installation, the well-operator,

shall ensure that the operation is not carried out, unless it is carried on in circumstances where the persons carrying out the operation have received such information, instruction and training, and are being so supervised, that the risk to health and safety from such operation is reduced to the lowest level that is reasonably practicable.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.