Regulation 33

SCHEDULE 4

Descriptions of information which certain persons may be required to furnish

PART I

1.  Estimates for any year or part of a year of–

(a)non-fossil fuel generating capacity available in pursuance of qualifying arrangements, expressed in megawatts;

(b)electricity from non-fossil fuel generating stations supplied in pursuance of qualifying arrangements, expressed in megawatt hours; and

(c)total amounts falling due under qualifying arrangements, expressed in pounds sterling, and the terms of any qualifying arrangements.

2.  Particulars of any changes expected to occur during the year in any total amounts falling due mentioned in paragraph 1(c).

3.  Estimates for any year or part of a year of–

(a)total quantities of electricity in each relevant category to be supplied by a licensed supplier, excluding quantities sold to other suppliers, as measured by a meter installed for the purpose at the point of supply and expressed in kilowatt hours;

(b)total quantities of electricity in each relevant category to be supplied by a licensed supplier, excluding quantities sold to other suppliers, without being measured by a meter, expressed in kilowatt hours, with particulars of the manner in which such quantities have been calculated;

(c)total quantities of leviable and other electricity to be delivered to a licensed supplier;

(d)total quantities of electricity delivered to any system of electric lines and electrical plant operated by a licensed supplier;

(e)loss factors applicable to, and actual kilowatt hours lost during, the conveyance of electricity by means of a system of electric lines and electrical plant operated by a licensed supplier;

(f)average revenue from the supply of electricity in each relevant category by a licensed supplier after deduction of value added tax and payments in respect of the levy, expressed in pence per kilowatt hour;

(g)total revenue, including the levy but excluding value added tax, from the supply of electricity in each relevant category;

(h)total quantities of electricity sold to a licensed supplier by another licensed supplier, expressed in kilowatt hours; and

(i)total quantities of electricity purchased by a licensed supplier–

(i)in circumstances where, in relation to a unit of electricity purchased for delivery during a particular half hour, no terms as to price, other than those at which any other licensed supplier would have been entitled to purchase such unit, are available to the supplier; and

(ii)in other circumstances.

4.  Estimates of the amounts of any advance payments or deferred payments to be made in any year, and of the dates upon which any such payments are to be made.

5.  Actual figures for any year or part of a year in respect of which an estimate has been, or could have been required to be, furnished.

6.  In so far as they are not within paragraphs 1 to 5, particulars of the matters mentioned in regulation 22(2).

7.  In the case of a licence under section 6(1)(c) or (2) of the Act granted after the coming into force of regulations 3 to 40 and 42, the date upon which the licence holder intends to start undertaking the activities authorised by the licence.

8.  The date upon which any licence holder intends to cease carrying on any activities authorised by his licence.

PART II

9.  Estimates for any year or part of a year of–

(a)the price a licensed supplier would have to pay for a unit of electricity purchased for delivery during a particular half hour and in relation to which no terms as to price, other than those at which any other licensed supplier would have been entitled to purchase that unit, are available;

(b)total quantities of leviable and other electricity delivered to or from a transmission system in England and Wales, expressed in kilowatt hours;

(c)total quantities of electricity delivered to a transmission system in England and Wales from–

(i)a transmission system in Scotland; or

(ii)an interconnector

expressed, in either case, in kilowatt hours; and

(d)loss factors applicable to, and actual kilowatt hours lost during, the conveyance of electricity by means of a transmission system in England and Wales.

10.  Actual figures for any year or part of a year in respect of which an estimate has been, or could have been required to be, furnished.

PART III

11.  Estimates for any year or part of a year of–

(a)the total quantities of electricity generated in non-fossil fuel generating stations to be acquired by each licensed supplier otherwise than in pursuance of qualifying arrange ments, as measured at the busbar side of the busbar selection isolators and expressed in kilowatt hours;

(b)total quantities of electricity generated in non-fossil fuel generating stations to be acquired pursuant to qualifying arrangements, as measured at the busbar side of the busbar selection isolators and expressed in kilowatt hours; and

(c)total quantities of electricity generated in fossil fuel generating stations to be acquired by each licensed supplier, as measured at the busbar side of the busbar selection isolators and expressed in kilowatt hours.

12.  Particulars of any changes expected to occur during the year in any total quantity mentioned in paragraph 10.

13.  In the case of a non-fossil generating station which is capable of being fuelled by a fossil fuel–

(a)a description of each type of fuel which may be used in the station;

(b)the quantities of each type of fuel estimated to be used in the station during a particular period; and

(c)the types, quantities and net calorific values of fuel actually used in the station during a particular period.

14.  Actual figures for any year or part of a year in respect of which an estimate has been, or could have been required to be, furnished.

Interpretation

15.  In paragraph 9(c)(ii) of this Schedule “interconnector” means a system of electric lines and plant by means of which electricity may be conveyed between the United Kingdom and any other country, or between England and Scotland.

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources