Notices about payments and performance

69Payments compliance notices

(1)Before the end of the period of 30 days beginning with the last day of a reporting period, a contracting authority must publish a payments compliance notice if during that period—

(a)the authority made a payment under a public contract;

(b)a sum owed by the authority under a public contract became payable.

(2)A “payments compliance notice” means a notice setting out—

(a)specified information about the contracting authority’s compliance with the term set out in section 68(2) (payment within 30 days), and

(b)any other specified information.

(3)For the purposes of this section, a reporting period is—

(a)the period beginning with the day on which this section comes into force and ending with the 31 March or 30 September following that day, whichever is earlier, and

(b)each successive period of six months.

(4)A Minister of the Crown or the Welsh Ministers may by regulations make provision about the preparation of a payments compliance notice, including provision requiring that the notice must be approved by a person of a description specified in the regulations.

(5)In subsection (2), “specified information” means information specified in regulations under section 95.

(6)This section does not apply—

(a)to a transferred Northern Ireland authority,

(b)to private utilities,

(c)in relation to a public contract awarded by a school, or

(d)in relation to a concession contract.

70Information about payments under public contracts

(1)A contracting authority must publish specified information about any payment of more than £30,000 made by the authority under a public contract.

(2)The information must be published before the end of the period of 30 days beginning with the last day of the quarter in which the payment was made.

(3)A Minister of the Crown or the Welsh Ministers may by regulations amend this section for the purpose of changing—

(a)the financial threshold;

(b)the time limit for publication.

(4)This section does not apply in relation to a public contract that is—

(a)a utilities contract awarded by a private utility,

(b)a concession contract,

(c)awarded by a school,

(d)awarded by a transferred Northern Ireland authority, unless it is awarded as part of a procurement under a reserved procurement arrangement or devolved Welsh procurement arrangement, or

(e)awarded as part of a procurement under a transferred Northern Ireland procurement arrangement.

(5)In this section—

  • quarter” means a period of three months ending with 31 March, 30 June, 30 September or 31 December in any year;

  • specified information” means information specified in regulations under section 95.

71Assessment of contract performance

(1)Subsection (2) applies where a contracting authority has set key performance indicators in accordance with section 52(1).

(2)At least once in every period of twelve months during the life-cycle of the contract and on termination of the contract the contracting authority must —

(a)assess performance against the key performance indicators, and

(b)publish information specified in regulations under section 95 in relation to that assessment.

(3)Subsection (5) applies if—

(a)a supplier has breached a public contract, and

(b)the breach results in—

(i)termination (or partial termination) of the contract,

(ii)the award of damages, or

(iii)a settlement agreement between the supplier and the contracting authority.

(4)Subsection (5) also applies if a contracting authority considers that a supplier—

(a)is not performing a public contract to the authority’s satisfaction,

(b)has been given proper opportunity to improve performance, and

(c)has failed to do so.

(5)Before the end of the period of 30 days beginning with the day on which this subsection first applies in relation to a particular breach or failure to perform, the contracting authority concerned must publish the following information—

(a)that this subsection applies,

(b)the circumstances giving rise to its application, and

(c)any other information specified in regulations under section 95.

(6)Subsection (5) does not apply in relation to a light touch contract.

(7)This section does not apply to private utilities.

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Show Explanatory Notes for Sections: Displays relevant parts of the explanatory notes interweaved within the legislation content.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Explanatory Notes

Text created by the government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes were introduced in 1999 and accompany all Public Acts except Appropriation, Consolidated Fund, Finance and Consolidation Acts.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources