4(1)The Development Corporation shall—
(a)before the commencement of impoundment, and
(b)during the period beginning two years, and ending three years, after the commencement of impoundment,
arrange for a survey of every building within the protected property area.
(2)The owner or occupier of, or of any part of, a building within the protected property area may during the period beginning three years, and ending twenty years, after the commencement of impoundment require the Development Corporation to arrange a survey of the building; but no more than one survey of a building may be required under this sub-paragraph.
(3)The owner or occupier of, or of any part of, a building within the protected property area may at any time during the period beginning with, and ending twenty years after, the commencement of impoundment when he is able to show a justifiable concern that the building has suffered or is likely to suffer groundwater damage require the Development Corporation to arrange a survey of the building.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: