Electricity Act 1989

 Help about what version

What Version

 Help about advanced features

Advanced Features

Status:

Point in time view as at 18/12/2011. This version of this provision has been superseded. Help about Status

Close

Status

You are viewing this legislation item as it stood at a particular point in time. A later version of this or provision, including subsequent changes and effects, supersedes this version.

Note the term provision is used to describe a definable element in a piece of legislation that has legislative effect – such as a Part, Chapter or section.

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to Electricity Act 1989. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Changes and effects yet to be applied by the editorial team are only applicable when viewing the latest version or prospective version of legislation. They are therefore not accessible when viewing legislation as at a specific point in time. To view the ‘Changes to Legislation’ information for this provision return to the latest version view using the options provided in the ‘What Version’ box above.

[F13A The principal objective and general duties of the Secretary of State and the Authority.E+W+S

(1)The principal objective of the Secretary of State and the Gas and Electricity Markets Authority (in this Act referred to as “the Authority”) in carrying out their respective functions under this Part is to protect the interests of [F2existing and future] consumers in relation to electricity conveyed by distribution systems [F3or transmission systems]F4... .

[F5(1A)Those interests of existing and future consumers are their interests taken as a whole, including—

(a)their interests in the reduction of electricity-supply emissions of targeted greenhouse gases; F6...

(b)their interests in the security of the supply of electricity to them[F7; and

(c)their interests in the fulfilment by the Authority, when carrying out its functions as designated regulatory authority for Great Britain, of the objectives set out in Article 36(a) to (h) of the Electricity Directive.]

(1B)The Secretary of State and the Authority shall carry out their respective functions under this Part in the manner which the Secretary of State or the Authority (as the case may be) considers is best calculated to further the principal objective, wherever appropriate by promoting effective competition between persons engaged in, or in commercial activities connected with, the generation, transmission, distribution or supply of electricity or the provision or use of electricity interconnectors.

(1C)Before deciding to carry out functions under this Part in a particular manner with a view to promoting competition as mentioned in subsection (1B), the Secretary of State or the Authority shall consider—

(a)to what extent the interests referred to in subsection (1) of consumers would be protected by that manner of carrying out those functions; and

(b)whether there is any other manner (whether or not it would promote competition as mentioned in subsection (1B)) in which the Secretary of State or the Authority (as the case may be) could carry out those functions which would better protect those interests.]

(2)[F8In performing the duties under subsections (1B) and (1C), the Secretary of State or the Authority shall have regard to]

(a)the need to secure that all reasonable demands for electricity are met; and

(b)the need to secure that licence holders are able to finance the activities which are the subject of obligations imposed by or under this Part[F9, the Utilities Act 2000[F10, Part 2 or 3 of the Energy Act 2004[F11, Part 2 or 5 of the Energy Act 2008 or section 4, Part 2, or sections 26 to 29 of the Energy Act 2010]]][F12; and

(c)the need to contribute to the achievement of sustainable development.]

(3)In performing [F13the duties under subsections (1B), (1C) and (2)], the Secretary of State or the Authority shall have regard to the interests of—

(a)individuals who are disabled or chronically sick;

(b)individuals of pensionable age;

(c)individuals with low incomes; and

(d)individuals residing in rural areas;

but that is not to be taken as implying that regard may not be had to the interests of other descriptions of consumer.

(4)The Secretary of State and the Authority may, in carrying out any function under this Part, have regard to—

(a)the interests of consumers in relation to gas conveyed through pipes (within the meaning of the M1Gas Act 1986); and

(b)any interests of consumers in relation to—

[F14(i)communications services and electronic communications apparatus, or]

(ii)water services or sewerage services (within the meaning of the M2Water Industry Act 1991),

which are affected by the carrying out of that function.

(5)Subject to [F15subsections (1B) and] (2), the Secretary of State and the Authority shall carry out their respective functions under this Part in the manner which he or it considers is best calculated—

(a)to promote efficiency and economy on the part of persons authorised by licences or exemptions to [F16distribute, supply or participate in the transmission of] electricity [F17or to participate in the operation of electricity interconnectors] and the efficient use of electricity conveyed by distribution systems [F18or transmission systems];

(b)to protect the public from dangers arising from the generation, transmission, distribution or supply of electricity;

F19(ba). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(c)to secure a diverse and viable long-term energy supply,

[F20and F21... shall], in carrying out those functions, have regard to the effect on the environment of activities connected with the generation, transmission, distribution or supply of electricity.

[F22(5A)In carrying out their respective functions under this Part in accordance with the preceding provisions of this section the Secretary of State and the Authority must each have regard to—

(a)the principles under which regulatory activities should be transparent, accountable, proportionate, consistent and targeted only at cases in which action is needed; and

(b)any other principles appearing to him or, as the case may be, it to represent the best regulatory practice.]

[F23(5B)In subsection (1A)—

  • emissions” has the same meaning as in the Climate Change Act 2008 (see section 97 of that Act);

  • electricity-supply emissions” in relation to emissions of a targeted greenhouse gas, means any such emissions (wherever their source) that are wholly or partly attributable to, or to commercial activities connected with, the generation, transmission, distribution or supply of electricity or the provision or use of electricity interconnectors;

  • targeted greenhouse gases” has the same meaning as in Part 1 of the Climate Change Act 2008 (see section 24 of that Act).]

(6)In [F24subsections [F25(1C),] (3) and (4) references to consumers include] both existing and future consumers.

(7)In this section and sections 3B and 3C, references to functions of the Secretary of State or the Authority under this Part include a reference to functions under the Utilities Act 2000 which relate to electricity conveyed by distribution systems [F26or transmission systems].

(8)In this Part, unless the context otherwise requires—

  • exemption” means an exemption granted under section 5;

  • licence” means a licence under section 6 and “licence holder” shall be construed accordingly.]

Textual Amendments

F1S. 3A substituted for s. 3 (20.12.2000) by 2000 c. 27, s. 13; S.I. 2000/3343, art. 2, Sch. (subject to transitional provisions in arts. 3-15) (as amended by S.I. 2001/1780, art. 2)

F2Words in s. 3A(1) inserted (26.1.2009) by Energy Act 2008 (c. 32), ss. 83(2)(a), 110(2); S.I. 2009/45, art. 2(d)(i)

F3Words in s. 3A(1) inserted (1.4.2006 for specified purposes, 1.4.2010 in so far as not already in force) by Energy Act 2004 (c. 20), s. 179(2)(3)(a), 198(2); S.I. 2005/2965, art. 3

F4Words in s. 3A(1) omitted (8.6.2010) by virtue of Energy Act 2010 (c. 27), ss. 17(2), 38(3)

F5Ss. 3A(1A)-(1C) inserted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(3), 38(3)

F8Words in s. 3A(2) substituted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(4)(a), 38(3)

F9Words in s. 3A(2)(b) substituted (24.8.2004 for specified purposes, 5.10.2004 in so far as not already in force) by Energy Act 2004 (c. 20), ss. 190(3), 198(2); S.I. 2004/2184, art. 2(1), Sch. 1; S.I. 2004/2575, art. 2(1), Sch. 1

F10Words in s. 3A(2)(b) substituted (26.11.2008) by Energy Act 2008 (c. 32), ss. 102(6), 110(2)

F11Words in s. 3A(2)(b) substituted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(4)(b), 38(3)

F12S. 3A(2)(c) and preceding word inserted (26.1.2009) by Energy Act 2008 (c. 32), ss. 83(2)(b), 110(2); S.I. 2009/45, art. 2(d)(i)

F13Words in s. 3A(3) substituted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(5), 38(3)

F14S. 3A(4)(b)(i) substituted (25.7.2003 for specified purposes, 29.12.2003 in so far as not already in force) by Communications Act 2003 (c. 21), s. 411(2), Sch. 17 para. 98 (with Sch. 18); S.I. 2003/1900, arts. 1(2), 2(1), Sch. 1 (with art. 3) (as amended by S.I. 2003/3142, art. 1(3)); S.I. 2003/3142, art. 3(2) (with art. 11)

F15Words in s. 3A(5) substituted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(6)(a), 38(3)

F16Words in s. 3A(5)(a) substituted (1.9.2004) by Energy Act 2004 (c. 20), s. 198(2), Sch. 19 para. 4; S.I. 2004/2184, art. 2(2), Sch. 2

F17Words in s. 3A(5)(a) inserted (1.12.2004) by Energy Act 2004 (c. 20), ss. 147(2)(b), 198(2); S.I. 2004/2575, art. 2(2), Sch. 2

F18Words in s. 3A(5)(a) inserted (1.4.2006 for specified purposes, 1.4.2010 in so far as not already in force) by Energy Act 2004 (c. 20), s. 179(2)(3)(a), 198(2); S.I. 2005/2965, art. 3

F20Words in s. 3A(5) substituted (5.10.2004) by Energy Act 2004 (c. 20), ss. 83(b), 198(2); S.I. 2004/2575, art. 2(1), Sch. 1

F21Words in s. 3A(5) omitted (8.6.2010) by virtue of Energy Act 2010 (c. 27), ss. 17(6)(b), 38(3)

F23S. 3A(5B) inserted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(7), 38(3)

F24Words in s. 3A(6) substituted (26.1.2009) by Energy Act 2008 (c. 32), ss. 83(2)(d), 110(2); S.I. 2009/45, art. 2(d)(i)

F25Word in s. 3A(6) inserted (8.6.2010) by Energy Act 2010 (c. 27), ss. 17(8), 38(3)

F26Words in s. 3A(7) inserted (1.4.2006 for specified purposes, 1.4.2010 in so far as not already in force) by Energy Act 2004 (c. 20), s. 179(2)(3)(a), 198(2); S.I. 2005/2965, art. 3

Modifications etc. (not altering text)

C1Ss. 3A-3D applied (24.8.2004 for specified purposes, 5.10.2004 in so far as not already in force) by Energy Act 2004 (c. 20), ss. 190(2), 198(2); S.I. 2004/2184, art. 2(1), Sch. 1; S.I. 2004/2575, art. 2(1), Sch. 1

C4Ss. 3A-3D applied (26.11.2008) by Energy Act 2008 (c. 32), ss. 102(4), 110(2)

C5Ss. 3A-3D applied (8.4.2010) by Energy Act 2010 (c. 27), ss. 30(2), 38(1)

C6Ss. 3A-3D applied (18.12.2011) by Energy Act 2011 (c. 16), ss. 78(2), 121(3)

C7Ss. 3A-3D applied (18.12.2011) by Energy Act 2011 (c. 16), ss. 98(14), 121(3)

Marginal Citations

Back to top

Options/Help

Print Options

You have chosen to open The Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act as a PDF

The Whole Act you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open The Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open The Whole Act without Schedules as a PDF

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.

Would you like to continue?

You have chosen to open the Whole Act

The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open the Whole Act without Schedules

The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

You have chosen to open Schedules only

The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.

Would you like to continue?

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Point in Time: This becomes available after navigating to view revised legislation as it stood at a certain point in time via Advanced Features > Show Timeline of Changes or via a point in time advanced search.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Impact Assessments

Impact Assessments generally accompany all UK Government interventions of a regulatory nature that affect the private sector, civil society organisations and public services. They apply regardless of whether the regulation originates from a domestic or international source and can accompany primary (Acts etc) and secondary legislation (SIs). An Impact Assessment allows those with an interest in the policy area to understand:

  • Why the government is proposing to intervene;
  • The main options the government is considering, and which one is preferred;
  • How and to what extent new policies may impact on them; and,
  • The estimated costs and benefits of proposed measures.
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources