Search Legislation

The Marine Licensing (Fees) (Scotland) Regulations 2011

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

Changes over time for: The Marine Licensing (Fees) (Scotland) Regulations 2011

 Help about opening options

Changes to legislation:

There are currently no known outstanding effects for The Marine Licensing (Fees) (Scotland) Regulations 2011. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

Scottish Statutory Instruments

2011 No. 78

Environmental Protection

Licensing (marine)

The Marine Licensing (Fees) (Scotland) Regulations 2011

Made

10th February 2011

Laid before the Scottish Parliament

14th February 2011

Coming into force

6th April 2011

The Scottish Ministers make the following Regulations in exercise of the powers conferred by sections 67(2) and (3)(b) and 316(1)(b) of the Marine and Coastal Access Act 2009(1) and sections 25(1)(b) and (2) and 165(1)(b) of the Marine (Scotland) Act 2010(2) and all other powers enabling them to do so.

Citation, commencement and interpretationS

1.—(1) These Regulations may be cited as the Marine Licensing (Fees) (Scotland) Regulations 2011 and come into force on 6th April 2011.

(2) In these Regulations—

“the 2009 Act” means the Marine and Coastal Access Act 2009;

“the 2010 Act” means the Marine (Scotland) Act 2010;

“application” means an application for a marine licence made under section 67 of the 2009 Act or under section 25 of the 2010 Act;

“capital dredging” means dredging which is carried out—

(a)

otherwise than in connection with maintenance works; and

(b)

in an area or down to a level not previously dredged during the preceding 7 years;

“renewable energy structure” means a structure in the Scottish marine area (within the meaning of section 1 of the 2010 Act) or in the Scottish offshore region (within the meaning of section 322(1) of the 2009 Act) constructed for the purposes of generating electricity.

Commencement Information

I1Reg. 1 in force at 6.4.2011, see reg. 1(1)

Determination of feesS

2.  The fee to accompany an application is to be determined—

(a)in accordance with regulations [F13, 4 and 5 (excluding regulation 5(5))] in the case of an application made before 1st April 2012;

[F2(aa)in accordance with regulation 3A or 5(5) in the case of an application made before 1st April 2013;]

(b)in accordance with regulation 6 in the case of an application made on or after [F31st April 2012 or, in the case of applications to which regulations 3A or 5(5) apply 1st April 2013].

Applications - generalS

3.—(1) This regulation applies to any application, other than one to which regulation [F43A,] 4 or 5 applies.

(2) Where in the opinion of the Scottish Ministers the activity for which a licence is sought forms part of a larger project, the fee is to be determined by reference to what the Scottish Ministers consider to be the likely cost of carrying out that project.

(3) Where the activity for which a licence is sought does not fall within paragraph (2), the fee is to be determined by reference to what the Scottish Ministers consider to be the likely cost of carrying out that activity.

(4) Where the likely cost of carrying out a project or activity (as the case may be)—

(a)is no greater than £2,500, the fee is £50;

(b)is greater than £2,500 but no greater than £5,000, the fee is £150;

(c)is greater than £5,000 but no greater than £50,000, the fee is £600;

(d)is greater than £50,000 but no greater than £2 million, the fee is £2,000;

(e)is greater than £2 million but no greater than £5 million, the fee is £4,000;

(f)is greater than £5 million but no greater than £20 million, the fee is £12,000;

(g)is greater than £20 million but no greater than £50 million, the fee is £20,000;

(h)is greater than £50 million, the fee is £30,000.

Textual Amendments

Commencement Information

I3Reg. 3 in force at 6.4.2011, see reg. 1(1)

[F5Applications – generating stationsS

3A.—(1) This regulation applies to an application for a licence in respect of any of the following actions required in relation to a renewable energy structure:—

(a)the deposit of any substance or object either in the sea or on or under the seabed;

(b)the construction, alteration or improvement of any works either in or over the sea or on or under the seabed; or

(c)the removal of any substance or object from the seabed.

(2) Where in the opinion of the Scottish Ministers the activity for which a licence is sought forms part of a larger project, the fee is to be determined by reference to what the Scottish Ministers consider to be the likely cost of carrying out that project.

(3) Where the activity for which a licence is sought does not fall within paragraph (2), the fee is to be determined by reference to what the Scottish Ministers consider to be the likely cost of carrying out that activity.

(4) Where the likely cost of carrying out a project or activity (as the case may be)—

(a)is no greater than £2,500, the fee is £52;

(b)is greater than £2,500 but no greater than £5,000, the fee is £155;

(c)is greater than £5,000 but no greater than £50,000, the fee is £620;

(d)is greater than £50,000 but no greater than £2 million, the fee is £2,760;

(e)is greater than £2 million but no greater than £5 million, the fee is £5,525;

(f)is greater than £5 million but no greater than £20 million, the fee is £16,545;

(g)is greater than £20 million but no greater than £50 million, the fee is £27,575;

(h)is greater than £50 million, the fee is £41,360.]

Applications – maintenance dredgingS

4.—(1) This regulation applies to an application for a licence in respect of the disposal of materials dredged from the seabed in connection with maintenance works.

(2) Where the application seeks a licence to dispose of no more than 10,000 tons over a period—

(a)of no more than 1 year, the fee is £1,400;

(b)of more than 1 year but no more than 2 years, the fee is £2,450;

(c)of more than 2 years but no more than 3 years, the fee is £3,500.

(3) Where the application seeks a licence to dispose of more than 10,000 tons but no more than 100,000 tons over a period—

(a)of no more than 1 year, the fee is £2,800;

(b)of more than 1 year but no more than 2 years, the fee is £4,900;

(c)of more than 2 years but no more than 3 years, the fee is £7,000.

(4) Where the application seeks a licence to dispose of more than 100,000 tons but no more than 300,000 tons over a period—

(a)of no more than 1 year, the fee is £5,600;

(b)of more than 1 year but no more than 2 years, the fee is £9,800;

(c)of more than 2 years but no more than 3 years, the fee is £14,000.

(5) Where the application seeks a licence to dispose of more than 300,000 tons over a period—

(a)of no more than 1 year, the fee is £9,400;

(b)of more than 1 year but no more than 2 years, the fee is £16,450;

(c)of more than 2 years but no more than 3 years, the fee is £23,500.

Commencement Information

I4Reg. 4 in force at 6.4.2011, see reg. 1(1)

Applications – capital dredgingS

5.—(1) This regulation applies to an application for a licence in respect of the disposal of materials dredged from the seabed in the course of capital dredging.

(2) Where the application seeks a licence to dispose of no more than 10,000 tons over a period—

(a)of no more than 1 year, the fee is £1,750;

(b)of more than 1 year but no more than 2 years, the fee is £3,500;

(c)of more than 2 years but no more than 3 years, the fee is £5,250.

(3) Where the application seeks a licence to dispose of more than 10,000 tons but no more than 100,000 tons over a period—

(a)of no more than 1 year, the fee is £3,500;

(b)of more than 1 year but no more than 2 years, the fee is £6,125;

(c)of more than 2 years but no more than 3 years, the fee is £8,750.

(4) Where the application seeks a licence to dispose of more than 100,000 tons but no more than 300,000 tons over a period—

(a)of no more than 1 year, the fee is £7,000;

(b)of more than 1 year but no more than 2 years, the fee is £12,250;

(c)of more than 2 years but no more than 3 years, the fee is £17,500.

(5) Where the application seeks a licence to dispose of more than 300,000 tons in connection with the construction of a renewable energy structure, the fee payable is [F6£34,475].

(6) In a case not falling within paragraph (5), where the application seeks a licence to dispose of more than 300,000 tons over a period—

(a)of no more than 1 year, the fee is £11,750;

(b)of more than 1 year but no more than 2 years, the fee is £20,562;

(c)of more than 2 years but no more than 3 years, the fee is £29,374.

Textual Amendments

Commencement Information

I5Reg. 5 in force at 6.4.2011, see reg. 1(1)

Applications made on or after 1st April 2012S

6.—(1) [F7Subject to paragraph (4), the] fees payable in respect of applications are to be varied with effect from 1st April each year and the fee to accompany an application made on or after 1st April 2012 is to be determined in accordance with paragraph (2).

(2) The fee payable in respect of an application is to be determined in accordance with the formula—

Where—

  • A is the amount that would have been payable had an application of the kind in question been made in the licensing year prior to the licensing year in which the application is made;

  • B is the Consumer Prices Index figure(3) for February in the licensing year immediately before the licensing year in which the application is made; and

  • C is the Consumer Prices Index figure for February in the licensing year finishing a year before the start of the licensing year in which the application is made.

(3) In paragraph (2), “licensing year” means a period of 12 months starting on 1st April.

[F8(4) In respect of applications made before 1st April 2013 and to which regulation 3A or 5(5) applies, paragraphs (1) and (2) apply with the modification that in paragraph (1) “1st April 2012” is to be read as “1st April 2013”.]

Reduced feeS

7.—(1) The Scottish Ministers may decide that a reduced fee is payable in respect of an application in the circumstances specified in paragraph (2).

(2) Those circumstances are where—

(a)an application is made which is, in the opinion of the Scottish Ministers, substantially similar to an earlier application; and

(b)that earlier application has been withdrawn or refused.

Commencement Information

I7Reg. 7 in force at 6.4.2011, see reg. 1(1)

RICHARD LOCHHEAD

A member of the Scottish Executive

St Andrew’s House,

Edinburgh

10th February 2011

EXPLANATORY NOTE

(This note is not part of the Regulations)

These Regulations make provision as to the fees payable in respect of applications to the Scottish Ministers for a marine licence. They apply to applications under both the Marine and Coastal Access Act 2009 (Scottish offshore waters) and the Marine (Scotland) Act 2010 (Scottish inshore waters).

Regulation 3 makes provision as to fees for all applications, other than applications for the disposal of materials dredged from the seabed (which are dealt with in regulations 4 and 5). Regulation 6 provides for the annual revision of fees as at 1st April by reference to changes in Consumer Prices Index figures. Regulation 7 allows the Scottish Ministers to charge a reduced fee in respect of a resubmitted application.

(3)

Consumer Prices Index figures can be obtained from the website of the Office for National Statistics (www.ons.gov.uk).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources