Search Legislation

The Renewables Obligation (Scotland) Order 2009

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Renewables Obligation (Scotland) Order 2009. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

PART 7Issue and revocation of SROCs

Issue of SROCs to generators and suppliers

34.—(1) Subject to paragraphs (2) to (4) and article 35 (issue of SROCs to agents), the Authority is to issue a SROC to the operator of the generating station by which the electricity to which the SROC relates was generated.

(2) Where electricity–

(a)is required to be generated by a generating station from renewable sources under a NFFO arrangement; or

(b)in compliance with such an arrangement, is required to be made available to the nominated person,

SROCs are to be issued as set out in paragraphs (3) and (4).

(3) Where by virtue of the NFFO arrangement the nominated person is entitled to the electricity, SROCs are to be issued to electricity suppliers notified to the Authority by the nominated person as being purchasers of the electricity and to each in such numbers as are appropriate to the amount of the electricity which the nominated person notifies the Authority each has purchased (subject to the total number of SROCs available to be issued in respect of the electricity).

(4) Where electricity suppliers are entitled to electricity under a NFFO arrangement, SROCs are to be issued to those electricity suppliers, each in proportion to its entitlement.

Issue of SROCs to agents

35.—(1) This article applies to a SROC which certifies the matters within section 32B(5), (6) or (8) of the Act (a “relevant SROC”).

(2) Where the generating stations to which a relevant SROC relates are operated by two or more persons (“the operators”), that SROC must be issued to an agent appointed for the purpose by the operators.

(3) The Authority must be notified in writing of the agent's appointment, name and address.

(4) That notification may be provided to the Authority by the operators (or any of them) or the agent.

(5) The Authority must be notified in writing if the agent's appointment is terminated.

(6) That notification may be provided to the Authority by the operators (or any of them) or the agent.

(7) Where notice is given under paragraph (5) and received by the Authority, the termination will take effect (subject to paragraph (8)) at the end of the obligation period during which it is given, and until the expiration of that obligation period the Authority must continue to issue any relevant SROCs to the agent.

(8) Notwithstanding paragraph (7), after the expiration of that obligation period the Authority must continue to issue relevant SROCs to the agent where those SROCs relate to electricity generated during that obligation period.

(9) Paragraphs (7) and (8) do not apply in any case where the Authority is satisfied, by evidence produced to it, that owing to exceptional circumstances the termination should have immediate effect.

(10) Where an agent's appointment has been terminated the agent is required to return to the operators any relevant information relating to the generation of electricity by their stations.

(11) Where any provision of this Order requires or permits something to be done by, to or in respect of an agent appointed under this article and the agent's appointment is terminated before that thing is done, references to that agent (however framed) are to be construed–

(a)where a successor to the agent has been appointed under this article, as references to that successor; and

(b)in any other case, as references to the operators of the generating stations for whom the agent acted before the appointment was terminated.

General criteria for the issue of SROCs

36.—(1) Subject to article 37, once during each obligation period the person to whom a SROC is to be issued must confirm to the Authority in writing, whether before or after the generation of the electricity to which the SROC relates, that that electricity, to the best of the person's knowledge and belief, has been or (as the case may be) will be–

(a)in the case of a SROC certifying the matters within section 32B(3) or (5) of the Act, supplied by a designated electricity supplier to customers in Great Britain;

(b)in the case of a SROC certifying the matters within section 32B(4) or (6) of the Act, supplied by a Northern Ireland supplier to customers in Northern Ireland; and

(c)in the case of a SROC certifying the matters within section 32B(7) or (8) of the Act, used in a permitted way.

(2) The electricity in respect of which a SROC is to be issued–

(a)must be generated during a month in which the generating station generating it is accredited under this Order or an Order made under Article 52 of the Northern Ireland Energy Order and any conditions to which the accreditation is subject are met;

(b)subject to paragraph (3), must be measured using a meter which, if used for ascertaining the quantity of electricity supplied by an authorised supplier to a customer, would be approved for the purposes of paragraph 2(1)(a) of Schedule 7 to the Act; and

(c)must not include electricity in respect of which a SROC–

(i)has already been issued under this Order and has not been revoked; or

(ii)has already been issued under an Order made under sections 32 to 32M of the Act by the Secretary of State (whether or not it has been revoked).

(3) Paragraph (2)(b) does not apply in relation to electricity generated by a generating station the operator of which has agreed with the Authority that estimates may be provided instead of measurements using a meter.

(4) Any information which–

(a)is relevant to the question whether a SROC is to be issued; and

(b)is requested by or required to be provided to the Authority under article 53 (provision of information to the Authority),

must be provided in the form and time requested and must be (in the Authority's opinion) accurate and reliable.

(5) Where such information relates to the fuel used in the generation of that electricity and the fuel did not originate at the generating station, in determining whether that information is accurate and reliable the Authority must have regard to–

(a)the distance over which the fuel was transported; and

(b)the conditions under which the fuel was prepared and transported.

[F1(6) The operator of a generating station which generates electricity by burning fuel in a combustion unit may notify the Authority in writing that, until such time as the notification is withdrawn, the energy content of any biomass burned in that combustion unit will be less than 50 per cent of the energy content of all the energy sources burned in that combustion unit.

(7) A notification under paragraph (6) constitutes sufficient evidence of the fact that the energy content of the biomass burned in the combustion unit referred to in the notification is less than 50 per cent of the energy content of all the energy sources burned in that combustion unit.

(8) A notification under paragraph (6) may be withdrawn by a notice—

(a)in writing from the operator of the generating station to the Authority; and

(b)which specifies a date from which the withdrawal of the notification is to take effect.]

Criteria applicable to SROCs where article 36(1)(a) or (b) cannot be complied with

37.—(1) Where a SROC certifying the matters within section 32B(3) or (5) of the Act is to be issued and article 36(1)(a) cannot be complied with because the electricity in respect of which the SROC is to be issued cannot be shown to have been supplied to customers in Great Britain, the person to whom the SROC is to be issued must confirm to the Authority in writing–

(a)that the electricity in question is to be regarded as having been supplied to customers in Great Britain by virtue of article 15(2) or (3); and

(b)where it is located otherwise than on land, that the generating station to which the SROC relates is connected directly to a transmission or distribution system (or the part of such a system) that is located in Northern Ireland (and to no other system or part thereof).

(2) Where a SROC certifying the matters within section 32B(4) or (6) of the Act is to be issued and article 36(1)(b) cannot be complied with because the electricity in respect of which the SROC is to be issued cannot be shown to have been supplied to customers in Northern Ireland, the person to whom the SROC is to be issued must confirm to the Authority in writing that the electricity in question is to be regarded as having been supplied to customers in Northern Ireland by virtue of article 15(4).

(3) In this article “Northern Ireland” has the same meaning as in Article 54(1) of the Northern Ireland Energy Order.

Further criterion applicable to SROCs certifying matters within section 32B(3) and (5) of the Act where electricity generated otherwise than on land

38.  Where a SROC certifying the matters within section 32B(3) or (5) of the Act is to be issued in relation to a generating station which is not located on land and the confirmation required by article 36(1)(a) has been or is to be given in relation to the electricity generated or to be generated by that station, the person to whom the SROC is to be issued must confirm to the Authority in writing that the generating station to which the SROC relates is connected directly to a transmission or distribution system in Great Britain and the electricity in respect of which it is to be issued cannot be or have been conveyed to Great Britain through an electricity interconnector.

Further criteria applicable to SROCs certifying matters within section 32B(3) to (6) of the Act

39.—(1) Once during each obligation period the person to whom a SROC certifying the matters within section 32B(3), (4), (5) or (6) is to be issued must confirm to the Authority in writing, whether before or after the generation of the electricity to which the SROC relates–

(a)that they are not a person who has been a party to an applicable NFFO arrangement (within the meaning of article 20);

(b)that they are not (and to the best of their knowledge and belief will not during the obligation period in which the confirmation is given become) a person who is a party to an applicable NFFO arrangement (within the meaning of article 21); and

(c)that they are not (and to the best of their knowledge and belief will not during the obligation period in which the confirmation is given become) a person who is a connected person or a linked person in relation to any such party.

(2) Paragraph (1) does not apply where the person to whom the SROC is to be issued is an electricity supplier.

Further criteria applicable to SROCs certifying matters within section 32B(5), (6) and (8) of the Act

40.—(1) Once during each obligation period the person to whom a SROC certifying the matters within section 32B(5), (6) or (8) is to be issued must confirm to the Authority in writing, whether before or after the generation of the electricity to which the SROC relates, the matters set out in paragraph (2).

(2) The matters set out in this paragraph are–

(a)that each of the generating stations in relation to which the SROC is to be issued–

(i)is a microgenerator; and

(ii)is accredited as a generating station capable of generating electricity in the same way from the same renewable source, and

(b)where the generating stations in relation to which the SROC is to be issued are operated by two or more persons (“the operators”), that the operators have each–

(i)appointed the person providing the confirmation to act as agent to receive the SROC on their behalf in accordance with article 35 (issue of SROCs to agents); and

(ii)agreed that their entitlement to SROCs should be determined in the same way (either on a monthly basis or on an annual basis, depending on whether or not a notice has been given to the Authority under article 60(2) (modifications of this Order in relation to microgenerators in certain circumstances)).

Refusing to issue and revoking SROCs

41.—(1) The Authority may refuse to issue a SROC–

(a)where any criterion in articles 36 to 40 which relates to that SROC is not (in its opinion) met;

(b)where any information referred to in article 36(4) or any confirmation provided to it under this Part is not (in its opinion) accurate and reliable.

(2) Where, in relation to any electricity generated by a generating station in a month, the Authority is satisfied that–

(a)any information referred to in article 36(4) is false;

(b)any confirmation provided to it under this Part is false; or

(c)a SROC was issued on the basis of any fraudulent behaviour, statement or undertaking on the part of–

(i)the operator of that generating station;

(ii)a connected person; or

(iii)where SROCs are issued to an agent by virtue of article 35, that agent,

the Authority [F2may] revoke all SROCs issued in respect of that electricity in that month.

[F3(3) The Authority must revoke any SROC which it has issued where the SROC certifies the matters within section 32B(4) or (6) of the Act and the Northern Ireland authority has notified the Authority that it is not satisfied that the electricity in respect of which the SROC was issued has been supplied to customers in Northern Ireland.]

(4) Where the Authority–

(a)is no longer satisfied that a SROC [F4is accurate or] should have been issued;

(b)has reasonable doubts as to the accuracy or reliability of the information upon which it relied prior to the issue of a SROC; or

(c)has been unable, due to a failure or refusal by any person (whether inside or outside Scotland) to provide it with any information reasonably requested by it, to check the accuracy of either a SROC or any information which it relied upon prior to the issue of a SROC,

it may revoke the SROC (or another SROC which is identical in all material respects and which has been issued to the same person).

[F5(5) In determining whether to revoke a SROC under paragraph (3) or (4), the Authority may disregard any changes to the amounts for RO input electricity (within the meaning of article 23A), RO output electricity (within the meaning of article 23A), total input electricity and total output electricity which were used by it to determine a generating station’s RO eligible renewable output in a month if satisfied that, in all the circumstances, it is reasonable for it to do so.]

(6) Where the Authority revokes a SROC it must delete that SROC from the Register and as soon as reasonably practicable afterwards give notice in writing of such revocation to the person who was the registered holder of the SROC at the time of its revocation.

[F6(7) This article is subject to article 41A(2) to (4).]

[F7Where SROCs cannot be revoked

41A.(1) A SROC cannot be revoked where it has been produced to the Authority under article 5 (the renewables obligation).

(2) A SROC cannot be revoked by the Authority under article 41(2) or (4) more than six years after it has been issued.

(3) Where the Authority would have revoked a SROC (“the original SROC”) under article 41(2) or (4) but for the fact that it has already been produced to it under article 5, the Authority must, subject to paragraph (4), refuse to issue a further SROC (“the further SROC”) in respect of electricity generated by the generating station in relation to which the original SROC was issued.

(4) The Authority shall refuse to issue the further SROC under paragraph (3) only if the original SROC was—

(a)issued no more than six years previously; and

(b)not issued to an electricity supplier under article 34(2) to (4).]

Textual Amendments

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources