The Renewables Obligation (Scotland) Order 2009

 Help about what version

What Version

 Help about advanced features

Advanced Features

Changes over time for: Section 28

 Help about opening options

Changes to legislation:

There are outstanding changes not yet made by the legislation.gov.uk editorial team to The Renewables Obligation (Scotland) Order 2009. Any changes that have already been made by the team appear in the content and are referenced with annotations. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. Changes and effects are recorded by our editorial team in lists which can be found in the ‘Changes to Legislation’ area. Where those effects have yet to be applied to the text of the legislation by the editorial team they are also listed alongside the legislation in the affected provisions. Use the ‘more’ link to open the changes and effects relevant to the provision you are viewing.

View outstanding changes

Changes and effects yet to be applied to the whole Instrument associated Parts and Chapters:

Whole provisions yet to be inserted into this Instrument (including any effects on those provisions):

[F1Electricity generated by qualifying combined heat and power generating stations

This section has no associated Executive Note

28.(1) This article applies to electricity—

(a)which is generated by a qualifying combined heat and power generating station in a way described in the first column of Part 2B of Schedule 2;

(b)to which none of articles 28A to 28E apply; and

(c)which is generated by a generating station to which article 29 does not apply.

(2) Subject to paragraphs (3) to (6), the amount of electricity to be stated in each SROC issued in respect of electricity to which this article applies is to be determined in accordance with article 27(4) to (8).

(3) Where electricity to which this article applies is generated using pre-2013 capacity, the amount of electricity to be stated in each SROC is—

(a)in respect of the qualifying proportion of that electricity, the amount of electricity in the second column of Part 2B of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule; and

(b)in respect of the remainder of that electricity, the amount of electricity in the third column of Part 2B of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule.

(4) Where a declaration has been made in accordance with paragraph (7) in respect of the 2013/15 capacity of a generating station, and electricity to which this article applies is generated by that station using 2013/15 capacity, the amount of electricity to be stated in each SROC is—

(a)in respect of the qualifying proportion of that electricity, the amount of electricity in the second column of Part 2B of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule; and

(b)in respect of the remainder of that electricity, the amount of electricity in the third column of Part 2B of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule.

(5) Where a declaration has been made in accordance with paragraph (7) in respect of the 2015/16 capacity of a generating station, and electricity to which this article applies is generated by that station using 2015/16 capacity, the amount of electricity to be stated in each SROC is—

(a)in respect of the qualifying proportion of that electricity, the amount of electricity in the second column of Part 2C of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule; and

(b)in respect of the remainder of that electricity, the amount of electricity in the third column of Part 2C of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule.

(6) Where a declaration has been made in accordance with paragraph (7) in respect of the post-2016 capacity of a generating station, and electricity to which this article applies is generated by that station using post-2016 capacity, the amount of electricity to be stated in each SROC is—

(a)in respect of the qualifying proportion of that electricity, the amount of electricity in the second column of Part 2D of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule; and

(b)in respect of the remainder of that electricity, the amount of electricity in the third column of Part 2D of Schedule 2 which corresponds to the description of the way in which the electricity is generated in the first column of that Part of that Schedule.

(7) A declaration is made in accordance with this paragraph if it meets the following conditions—

(a)it is made by the operator of the generating station to the Authority in writing;

(b)it is made in respect of the 2013/15 capacity, 2015/16 capacity or post-2016 capacity of the station;

(c)in the case of a declaration made in respect of the 2013/15 capacity of the station, it confirms that—

(i)2013/15 capacity forms part of the total installed capacity of the station; and

(ii)support has not been given under any relevant scheme for heat produced by the use of that generating capacity;

(d)in the case of a declaration made in respect of the 2015/16 capacity of the station, it confirms that—

(i)2015/16 capacity forms part of the total installed capacity of the station; and

(ii)none of the heat produced by the use of the 2015/16 capacity is eligible for support under a relevant scheme for reasons that include one or both of the following—

(aa)the way in which the station generates electricity;

(bb)the biomass, bioliquid or energy crops used by the station to generate electricity;

(e)in the case of a declaration made in respect of the post-2016 capacity of the station, it confirms that—

(i)post-2016 capacity forms part of the total installed capacity of the station; and

(ii)none of the heat produced by the use of the post-2016 capacity is eligible for support under a relevant scheme for reasons that include one or both of the following—

(aa)the way in which the station generates electricity;

(bb)the biomass, bioliquid or energy crops used by the station to generate electricity; and

(f)it states that, for so long as the station generates electricity in respect of which SROCs may be issued, the operator of the station will not claim support under any relevant scheme for heat produced by the station using the type of generating capacity in respect of which the declaration is made.

(8) A declaration made in accordance with paragraph (7) cannot be withdrawn.

(9) In this article “relevant scheme” means a scheme established by the Secretary of State in exercise of the power in section 100(1)(a) of the Energy Act 2008.

(10) This article is subject to article 32.]

Textual Amendments

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

Executive Note

Executive Note sets out a brief statement of the purpose of a Scottish Statutory Instrument and provides information about its policy objective and policy implications. They aim to make the Scottish Statutory Instrument accessible to readers who are not legally qualified and accompany any Scottish Statutory Instrument or Draft Scottish Statutory Instrument laid before the Scottish Parliament from July 2005 onwards.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different points in time where a change occurred. The dates will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. The first date in the timeline will usually be the earliest date when the provision came into force. In some cases the first date is 01/02/1991 (or for Northern Ireland legislation 01/01/2006). This date is our basedate. No versions before this date are available. For further information see the Editorial Practice Guide and Glossary under Help.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as made version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources