48.—(1) This regulation applies where—
(a)before the relevant date a public electricity supplier and a person who has requested the said supplier to provide a connection to any premises have agreed to enter into an agreement as mentioned in Article 25 of the 1992 Order; and
(b)the parties have not by that date entered into an agreement.
(2) On and after the relevant date the distribution successor and the person requesting the connection shall be deemed to have agreed to enter into a special connection agreement as mentioned in Article 25(1) of the 1992 Order as it had effect on or after that date.
(3) Any connection made by a distribution successor as a result of the application of paragraph (2) shall be a connection made in pursuance of Article 22 of the 1992 Order as it had effect after the relevant date.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As Enacted or Made): The original version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: