Section 32 – Inspection timing: other qualifications

The second special case is where a construction engineer is to be commissioned to supervise relevant works for the construction or alteration of a high or medium consequence reservoir. The construction engineer also supervises the safety of the reservoir (section 43(3)).

Where a reservoir is being discontinued or abandoned, any inspection which is due under section 30 or 31 is not required as it ceases to be a controlled reservoir on completion of the works i.e. when the final certificate is issued (subsection (1)).

Where a controlled reservoir is being constructed or altered (without being discontinued or abandoned), any inspection due under section 30 or 31 is not required; and instead inspection must be within 2 years from the date of the final certificate or at an earlier time, if recommended in the final certificate (subsection (2)).

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Northern Ireland Assembly department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of the Northern Ireland Assembly.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources