Section 25 - Supervision requirements and commissioning of supervising engineer etc
Section 25 requires a high or medium consequence reservoir to be under the supervision of a supervising engineer at all times i.e. on an ongoing basis. A supervising engineer must be commissioned within 6 months of the reservoir designation taking effect and a reservoir manager is required to give notice to the Department within 28 days of the commissioning. A supervising engineer must be an appropriate panel engineer. Unlike other reservoir engineers under the Act, there is nothing to prevent a supervising engineer being an employee of the reservoir manager or having previously been a construction engineer or inspecting engineer in relation to the reservoir.
A supervising engineer remains in place alongside the construction engineer when a high or medium consequence reservoir is undergoing alteration (work for which provision is made in part 3). This is to ensure that the safety of the reservoir continues to be monitored where appropriate and in particular the matters included in a safety report, prepared by the construction engineer, are monitored until a final certificate is issued.