Commission Regulation (EU) 2017/459Show full title

Commission Regulation (EU) 2017/459 of 16 March 2017 establishing a network code on capacity allocation mechanisms in gas transmission systems and repealing Regulation (EU) No 984/2013 (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

 Help about opening options

Opening Options

 Help about UK-EU Regulation

Legislation originating from the EU

When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.

Close

This item of legislation originated from the EU

Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).

Changes to legislation:

There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/459, CHAPTER I. Help about Changes to Legislation

Close

Changes to Legislation

Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.

CHAPTER IU.K. GENERAL PROVISIONS

Article 1U.K.Subject matter

This Regulation establishes a network code setting up capacity allocation mechanisms in gas transmission systems for existing and incremental capacity. [F1This Regulation set outs how transmission system operators cooperate with adjacent TSOs in] order to facilitate capacity sales, having regard to general commercial as well as technical rules related to capacity allocation mechanisms.

Article 2U.K.Scope

1.This Regulation shall apply to interconnection points [F2where transmission system operators carry out functions or activities that are regulated by a national regulatory authority]. It may also apply to entry points from and exit points to [F3other] countries, subject to the decision of the relevant national regulatory authority. This Regulation shall not apply to exit points to end consumers and distribution networks, entry points from ‘liquefied natural gas’ (LNG) terminals and production facilities, and entry points from or exit points to storage facilities.

2.The standardised capacity allocation mechanisms [F4provided for in] this Regulation shall include an auction procedure for relevant interconnection points F5... and the standard capacity products to be offered and allocated. Where incremental capacity is offered, alternative allocation mechanisms may also be used, subject to the conditions set out in Article 30(2).

3.This Regulation shall apply to all technical and interruptible capacity at interconnection points as well as to additional capacity in the meaning of point 2.2.1 of Annex I of Regulation (EC) No 715/2009 and to incremental capacity. [F6This Regulation does not apply to interconnection points where, immediately before IP completion day, either the UK or relevant member State held a derogation on the basis of Article 49 of Directive 2009/73/EC, as it had effect in EU law.]

4.Where an alternative capacity allocation mechanism according to Article 30 is applied, Article 8(1) to (7), Articles 11 to 18, Article 19(2) and Article 37 shall not be applicable to the offer levels, unless decided otherwise by the relevant national regulatory authorities.

5.Where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37.

6.In order to prevent foreclosure of downstream supply markets, national regulatory authorities may, after consulting network users, decide to take proportionate measures to limit up-front bidding for capacity by any single network user at interconnection points F7....

Article 3U.K.Definitions

For the purposes of this Regulation, the definitions in Article 2 of Regulation (EC) No 715/2009, Article 3 of Commission Regulation (EU) 2017/460(1) F8... shall apply. In addition, the following definitions shall apply:

1.

‘incremental capacity’ means a possible future increase via market-based procedures in technical capacity or possible new capacity created where none currently exists that may be offered based on investment in physical infrastructure or long-term capacity optimisation and subsequently allocated subject to the positive outcome of an economic test, in the following cases:

(a)

at existing interconnection points;

(b)

by establishing a new interconnection point or points;

(c)

as physical reverse flow capacity at an interconnection point or points, which has not been offered before;

2.

‘interconnection point’ means a physical or virtual point connecting adjacent entry-exit systems or connecting an entry-exit system with an interconnector, in so far as these points are subject to booking procedures by network users;

3.

‘alternative allocation mechanism’ means an allocation mechanism for offer level or incremental capacity designed on a case-by-case basis by the transmission system operators, and approved by the national regulatory authorities, to accommodate conditional demand requests;

4.

‘standard capacity product’ means a certain amount of transport capacity over a given period of time, at a specified interconnection point;

5.

‘offer level’ means the sum of the available capacity and the respective level of incremental capacity offered for each of the yearly standard capacity products at an interconnection point;

6.

‘implicit allocation method’ means a capacity allocation method where, possibly by means of an auction, both transmission capacity and a corresponding quantity of gas are allocated at the same time;

7.

‘bidding round’ means the period of time during which network users can submit, amend and withdraw bids;

8.

‘large price step’ means a fixed or variable amount that is defined per interconnection point and standard capacity product;

9.

‘incremental capacity project’ means a project to increase the amount of technical capacity at an existing interconnection point or to establish a new interconnection point based on capacity allocation in the preceding incremental capacity process;

10.

‘economic test’ means a test applied to assess the economic viability of incremental capacity projects;

11.

‘incremental capacity process’ means a process to assess the market demand for incremental capacity that includes a non-binding phase, in which network users express and quantify their demand for incremental capacity, and a binding phase, in which binding commitments for contracting capacity are requested from network users by one or more transmission system operators;

12.

‘bundled capacity’ means a standard capacity product offered on a firm basis which consists of corresponding entry and exit capacity at both sides of every interconnection point;

13.

‘interconnection agreement’ means an agreement entered into by [F9a transmission system operator with an adjacent TSO], whose systems are connected at a particular interconnection point, which specifies terms and conditions, operating procedures and provisions, in respect of delivery and/or withdrawal of gas at the interconnection point with the purpose of facilitating efficient interoperability of the interconnected transmission networks, as set out in Chapter II of Regulation (EU) 2015/703;

14.

‘competing capacities’ means capacities for which the available capacity at one point of the network cannot be allocated without fully or partly reducing the available capacity at another point of the network;

15.

‘auction calendar’ means a table displaying information relating to specific auctions which is published [F10jointly by, or on behalf of, all transmission system operators] by January of every calendar year for auctions taking place during the period of March until February of the following calendar year and consisting of all relevant timings for auctions, including starting dates and standard capacity products to which they apply;

16.

‘gas day’ means the period from [F115.00 a.m. to 5.00 a.m. the following day];

17.

‘within-day capacity’ means capacity offered and allocated after the closure of the day-ahead capacity auctions with respect to that day;

18.

‘ascending clock auction’ means an auction in which a network user places requested quantities against defined price steps, which are announced sequentially;

19.

‘uniform-price auction’ means an auction in which the network user in a single bidding round bids price as well as quantity and all network users, who are successful in gaining capacity, pay the price of the lowest successful bid;

20.

‘reserve price’ means the eligible floor price in the auction;

21.

‘small price step’ means a fixed or variable amount that is defined per interconnection point and standard capacity product which is smaller than the large price step;

22.

‘first-time undersell’ means an occurrence where the aggregate demand across all network users is less than the capacity offered at the end of the second bidding round or a subsequent bidding round;

23.

‘virtual interconnection point’ means two or more interconnection points which connect the same two adjacent entry-exit systems, integrated together for the purposes of providing a single capacity service;

24.

‘f-factor’ means the share of the present value of the estimated increase in the allowed or target revenue of the transmission system operator associated with the incremental capacity included in the respective offer level as set out in Article 22(1)(b) to be covered by the present value of binding commitments of network users for contracting capacity calculated as set out in Article 22(1)(a);

25.

‘over-nomination’ means the entitlement of network users who fulfil minimum requirements for submitting nominations to request interruptible capacity at any time within-day by submitting a nomination which increases the total of their nominations to a level higher than their contracted capacity;

26.

[F12‘non-UK regulatory authority’ means a regulatory authority for a country or territory other than the UK;

27.

‘adjacent TSO’ means a transmission system operator or a non-UK TSO which operates a transmission system which is directly connected to a transmission system operated by the relevant transmission system operator.]

(1)

Commission Regulation (EU) 2017/460 of 16 March 2017 establishing a network code on harmonised transmission tariff structures for gas (see page 29 of this Official Journal).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources