Commission Regulation (EU) 2017/1485 of 2 August 2017 establishing a guideline on electricity transmission system operation (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) 2017/1485, Article 45.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.Each SGU which is a power generating facility owner of a type D power generating module connected to the transmission system shall provide the TSO with at least the following data:
(a)general data of the power generating module, including installed capacity and primary energy source;
(b)turbine and power generating facility data including time for cold and warm start;
(c)data for short-circuit current calculation;
(d)power generating facility transformer data;
(e)FCR data of power generating modules offering or providing that service, in accordance with Article 154;
(f)FRR data of power generating modules offering or providing that service, in accordance with Article 158;
(g)RR data of power generating modules that offer or provide that service in accordance with Article 161;
(h)data necessary for restoration of the transmission system;
(i)data and models necessary for performing dynamic simulation;
(j)protection data;
F1(k). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(l)voltage and reactive power control capability.
2.Each SGU which is a power generating facility owner of a type B or a type C power generating module connected to the transmission system shall provide the TSO with at least the following data:
(a)general data of the power generating module, including installed capacity and primary energy source;
(b)data for short-circuit current calculation;
(c)FCR data F2... for power generating modules offering or providing that service;
(d)FRR data for power generating modules that offer or provide that service;
(e)RR data for power generating modules that offer or provide that service;
(f)protection data;
(g)reactive power control capability;
F3(h). . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
(i)data necessary for performing dynamic stability assessment according to Article 38.
3.A TSO may request the power generating facility owner of a power generating module connected to the transmission system to provide further data where appropriate for operational security analysis in accordance with Title 2 of Part III.
4.Each HVDC system owner or interconnector owner shall provide the TSO with the following data regarding the HVDC system or interconnector:
(a)nameplate data of the installation;
(b)transformers data;
(c)data on filters and filter banks;
(d)reactive power compensation data;
(e)active power control capability;
(f)reactive power and voltage control capability;
(g)active or reactive operational mode prioritization, if existing;
(h)frequency response capability;
(i)dynamic models for dynamic simulation;
(j)protection data; and
(k)fault-ride-through capability.
5.Each AC interconnector owner shall provide the TSO with at least the following data:
(a)nameplate data of the installation;
(b)electrical parameters;
(c)associated protections.
Textual Amendments
F1Art. 45(1)(k) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 39(2) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Art. 45(2)(c) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 39(3)(a) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
F3Art. 45(2)(h) omitted (E.W.S.) (31.12.2020) by virtue of The Electricity Network Codes and Guidelines (System Operation and Connection) (Amendment etc.) (EU Exit) Regulations 2019 (S.I. 2019/533), reg. 1(2), Sch. 1 para. 39(3)(b) (as amended by S.I. 2020/1016, regs. 1(2), 6(2)); 2020 c. 1, Sch. 5 para. 1(1)
The Whole Regulation you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: