- Latest available (Revised)
- Original (As adopted by EU)
Commission Regulation (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity markets and amending Annex I to Regulation (EC) No 714/2009 of the European Parliament and of the Council (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Regulation (EU) No 543/2013, Article 7.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
1.For their control areas, TSOs shall [F1publish] the following information F2...:
(a)the planned unavailability of 100 MW or more of a consumption unit, including changes of 100 MW or more in the planned unavailability of consumption units, lasting at least one market time unit, specifying:
(a)bidding zone,
available capacity per market time unit during the event,
reason for the unavailability,
the estimated start and end date (day, hour) of the change in availability;
(b)changes in actual availability of a consumption unit with a power rating of 100 MW or more, specifying:
(b)bidding zone,
available capacity per market time unit during the event,
reason for the unavailability,
the start date and the estimated end date (day, hour) of the change in availability.
2.The information laid down in point (a) of paragraph 1 shall be published in aggregated form per bidding zone indicating the sum of unavailable consumption capacity per market time unit during a given period as soon as possible but no later than one hour after the decision regarding the planned unavailability is made.
The information laid down point (b) of paragraph 1 shall be published in aggregated form per bidding zone indicating the sum of unavailable consumption capacity per market time unit during a given period as soon as possible but no later than one hour after the change in actual availability.
3.Consumption units located in a TSO’s control area shall calculate and submit the data laid down in paragraph 1 to that TSO.
The consumption units shall be considered as primary owner of the data they submit.
Textual Amendments
F1Word in Art. 7(1) substituted (31.12.2020) by The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 6(a); 2020 c. 1, Sch. 5 para. 1(1)
F2Words in Art. 7(1) omitted (31.12.2020) by virtue of The Electricity and Gas (Market Integrity and Transparency) (Amendment) (EU Exit) Regulations 2019 (S.I. 2019/534), reg. 1(2), Sch. 3 para. 6(b); 2020 c. 1, Sch. 5 para. 1(1)
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: