Search Legislation

Directive 2009/31/EC of the European Parliament and of the CouncilShow full title

Directive 2009/31/EC of the European Parliament and of the Council of 23 April 2009 on the geological storage of carbon dioxide and amending Council Directive 85/337/EEC, European Parliament and Council Directives 2000/60/EC, 2001/80/EC, 2004/35/EC, 2006/12/EC, 2008/1/EC and Regulation (EC) No 1013/2006 (Text with EEA relevance)

 Help about what version

What Version

 Help about advanced features

Advanced Features

More Resources

Close

This is a legislation item that originated from the EU

After exit day there will be three versions of this legislation to consult for different purposes. The legislation.gov.uk version is the version that applies in the UK. The EU Version currently on EUR-lex is the version that currently applies in the EU i.e you may need this if you operate a business in the EU.

The web archive version is the official version of this legislation item as it stood on exit day before being published to legislation.gov.uk and any subsequent UK changes and effects applied. The web archive also captured associated case law and other language formats from EUR-Lex.

Status:

EU Directives are being published on this site to aid cross referencing from UK legislation. After IP completion day (31 December 2020 11pm) no further amendments will be applied to this version.

ANNEX IIU.K.CRITERIA FOR ESTABLISHING AND UPDATING THE MONITORING PLAN REFERRED TO IN ARTICLE 13(2) AND FOR POST-CLOSURE MONITORING

1.Establishing and updating the monitoring planU.K.

The monitoring plan referred to in Article 13(2) shall be established according to the risk assessment analysis carried out in Step 3 of Annex I, and updated with the purpose of meeting the monitoring requirements laid out in Article 13(1) according to the following criteria:U.K.

1.1.Establishing the planU.K.

The monitoring plan shall provide details of the monitoring to be deployed at the main stages of the project, including baseline, operational and post-closure monitoring. The following shall be specified for each phase:

(a)

parameters monitored;

(b)

monitoring technology employed and justification for technology choice;

(c)

monitoring locations and spatial sampling rationale;

(d)

frequency of application and temporal sampling rationale.

The parameters to be monitored are identified so as to fulfil the purposes of monitoring. However, the plan shall in any case include continuous or intermittent monitoring of the following items:

(e)

fugitive emissions of CO2 at the injection facility;

(f)

CO2 volumetric flow at injection wellheads;

(g)

CO2 pressure and temperature at injection wellheads (to determine mass flow);

(h)

chemical analysis of the injected material;

(i)

reservoir temperature and pressure (to determine CO2 phase behaviour and state).

The choice of monitoring technology shall be based on best practice available at the time of design. The following options shall be considered and used as appropriate:

(j)

technologies that can detect the presence, location and migration paths of CO2 in the subsurface and at surface;

(k)

technologies that provide information about pressure-volume behaviour and areal/vertical distribution of CO2-plume to refine numerical 3-D simulation to the 3-D-geological models of the storage formation established pursuant to Article 4 and Annex I;

(l)

technologies that can provide a wide areal spread in order to capture information on any previously undetected potential leakage pathways across the areal dimensions of the complete storage complex and beyond, in the event of significant irregularities or migration of CO2 out of the storage complex.

1.2.Updating the planU.K.

The data collected from the monitoring shall be collated and interpreted. The observed results shall be compared with the behaviour predicted in dynamic simulation of the 3-D-pressure-volume and saturation behaviour undertaken in the context of the security characterisation pursuant to Article 4 and Annex I Step 3.

Where there is a significant deviation between the observed and the predicted behaviour, the 3-D model shall be recalibrated to reflect the observed behaviour. The recalibration shall be based on the data observations from the monitoring plan, and where necessary to provide confidence in the recalibration assumptions, additional data shall be obtained.

Steps 2 and 3 of Annex I shall be repeated using the recalibrated 3-D model(s) so as to generate new hazard scenarios and flux rates and to revise and update the risk assessment.

Where new CO2 sources, pathways and flux rates or observed significant deviations from previous assessments are identified as a result of history matching and model recalibration, the monitoring plan shall be updated accordingly.

2.Post-closure monitoringU.K.

Post-closure monitoring shall be based on the information collected and modelled during the implementation of the monitoring plan referred to in Article 13(2) and above in point 1.2 of this Annex. It shall serve in particular to provide information required for the determination of Article 18(1).

Back to top

Options/Help

Print Options

Close

Legislation is available in different versions:

Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.

Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.

Close

See additional information alongside the content

Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.

Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.

Close

Opening Options

Different options to open legislation in order to view more content on screen at once

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the EU Official Journal
  • lists of changes made by and/or affecting this legislation item
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources
Close

Timeline of Changes

This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.

The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.

For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.

Close

More Resources

Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as adopted version that was used for the print copy
  • correction slips

Click 'View More' or select 'More Resources' tab for additional information including:

  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • links to related legislation and further information resources