Commission Implementing Decision (EU) 2020/248 of 21 February 2020 laying down technical guidelines for inspections in accordance with Article 17 of Directive 2006/21/EC of the European Parliament and of the Council (notified under document C(2020) 889) (Text with EEA relevance)
When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
There are currently no known outstanding effects by UK legislation for Commission Implementing Decision (EU) 2020/248.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union,
Having regard to Directive 2006/21/EC of the European Parliament and of the Council of 15 March 2006 on the management of waste from extractive industries and amending Directive 2004/35/EC(1), and in particular Article 22(1)(c) thereof,
Whereas:
(1) Article 17 of Directive 2006/21/EC requires inspections of any waste facility covered by Article 7 in that Directive in order to ensure that it complies with the relevant conditions of the permit. In order for those inspections to be efficient and effective, competent authorities should be appropriately resourced, independent from the operators of the waste facilities concerned, vested with the necessary functions and powers and entitled to assistance from operators. Inspection activities should also involve co-operation and co-ordination between national authorities responsible for ensuring that waste facilities in their jurisdiction comply with the provisions set out in Directive 2006/21/EC.
(2) In order for the inspections to be efficient and proactive, it is appropriate that they are planned in advance by means of inspection plans reflecting the risks presented by the waste facilities concerned.
(3) As the waste facilities covered by Article 7 of Directive 2006/21/EC include waste facilities which ought to have a permit and, as Article 7 provides that no waste facility should operate without a permit, it is necessary for the inspection plans to take account of those waste facilities which ought to have a permit but do not hold one.
(4) Member States should retain a margin of discretion in the application of the inspection guidelines having regard to the different circumstances of each waste facility, to ensure that inspections are proportionate to the relevant environmental and safety risks presented by each waste facility.
(5) In order to address different situations of possible non-compliance with permits, provision should be made for both routine inspections and non-routine inspections to respond to serious complaints, accidents, incidents and occurrences of non-compliance. When carrying out the inspections, the inspectors should also take account of the findings of inspections carried out under other applicable EU legislation to the extent that those findings may also indicate possible problems with the permit requirements under Article 7 of Directive 2006/21/EC.
(6) In order to ensure the effectiveness of the inspections, it is necessary that a certain proportion of inspection activities, and in particular site visits, are unannounced.
(7) In order to make it possible to draw conclusions from inspection activities, in particular site visits, and to provide an empirical basis for future inspections and other related measures, it is important that all inspection activities are properly documented, including through regular site visit reports.
(8) In order to effectively ensure compliance with permit conditions, it is important that inspections facilitate and enable any further measures to respond to detected non-compliance.
(9) Given that risks vary depending on the stage of existence of the concerned waste facilities, it is necessary that the technical guidelines contain detailed provisions concerning the different life phases of waste facilities covered by Article 7 of Directive 2006/21/EC.
(10) Given that Category A waste facilities pose potentially higher risks, it is necessary that the technical guidelines contain specific provisions in respect of such facilities.
(11) The measures provided for in this Decision are in accordance with the opinion of the Committee established in accordance with Article 23(2) of Directive 2006/21/EC,
HAS ADOPTED THIS DECISION:
Modifications etc. (not altering text)
C1Decision: power to modify conferred (26.2.2022) by The Waste and Agriculture (Legislative Functions) Regulations 2022 (S.I. 2022/190), regs. 1(1), 10(1)(2)(e)
[F11.]The technical guidelines for inspections of [F2mining waste facilities] set out in the Annex to this Decision are adopted.
[F32.In this Decision—
“the Mining Waste Directive” means Directive 2006/21/EC of the European Parliament and of the Council on the management of waste from extractive industries, read with the modifications in Article 1A;
“the Waste Framework Directive” means Directive 2008/98/EC of the European Parliament and of the Council on waste, as last amended by Directive (EU) 2018/851;
“Category A facility” or “Category A waste facility” means a mining waste facility classified as Category A in accordance with the criteria in Annex 3 to the Mining Waste Directive;
“competent authority” means an authority responsible for carrying out inspections of mining waste facilities under the inspection provisions;
“the inspection provisions” means the provisions of the relevant mining waste legislation which, immediately before IP completion day, implemented Article 17 of the Mining Waste Directive;
“mining waste facility” or “waste facility”—
in relation to England and Wales, has the meaning given to “mining waste facility” by paragraph 2(1) of Schedule 20 to the Environmental Permitting (England and Wales) Regulations 2016;
in relation to Scotland, has the meaning given to “waste facility” by regulation 2(1) of the Management of Extractive Waste (Scotland) Regulations 2010;
in relation to Northern Ireland, has the meaning given to “waste facility” by regulation 2(2) of the Planning (Management of Waste from Extractive Industries) Regulations (Northern Ireland) 2015;
“the relevant mining waste legislation” means—
in relation to England and Wales, Schedule 20 to the Environmental Permitting (England and Wales) Regulations 2016;
in relation to Scotland, the Management of Extractive Waste (Scotland) Regulations 2010;
in relation to Northern Ireland, the Planning (Management of Waste from Extractive Industries) Regulations (Northern Ireland) 2015;
“waste management plan” has the meaning given in the relevant mining waste legislation.
3.Other expressions used in this Decision which are defined in the Mining Waste Directive have the meanings given in that Directive.]
Textual Amendments
F1Art. 1 renumbered as Art. 1(1) (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(2)(a)
F2Words in Art. 1(1) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(2)(b)
F3Art. 1(2)(3) inserted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(2)(c)
1.For the purposes of Article 1(2) and (3), the Mining Waste Directive is to be read with the modifications in paragraphs 2 and 3.
2.Article 3 is to be read as if—
(a)in point (1), for “Article 1(a) of Directive 75/442/EEC” there were substituted “Article 3(1) of the Waste Framework Directive, as read with Articles 5 and 6 of that Directive”;
(b)in point (2), for “Article 1(4) of Council Directive 91/689/EEC of 12 December 1991 on hazardous waste” there were substituted “Article 3(2) of the Waste Framework Directive”;
(c)in point (24), the words from “in accordance” to “takes place,” were omitted;
(d)point (27) were omitted.
3.Annex 3 is to be read as if—
(a)in the second indent, for “Directive 91/689/EEC” there were substituted “the Waste Framework Directive”;
(b)in the third indent, for “Directives 67/548/EEC or 1999/45/EC” there were substituted “Regulation (EC) 1272/2008 of the European Parliament and of the Council on classification, labelling and packaging of substances and mixtures”.
Textual Amendments
1.For the purposes of Article 1A, “the Waste Framework Directive” means Directive 2008/98/EC of the European Parliament and of the Council on waste, as last amended by Directive (EU) 2018/851, and read with the modifications in paragraphs 2 to 4.
2.Article 5 is to be read as if—
(a)in paragraph 1, “Member States shall take appropriate measures to ensure that” were omitted;
(b)after paragraph 1 there were inserted—
Any decision as to whether a substance or object is a by-product must be made—
(a)in accordance with any regulations setting out detailed criteria on the application of the conditions in paragraph 1 to specific substances or objects; and
(b)having regard to any guidance published by the appropriate authority or the appropriate agency for the purposes of this Article.”;
(c)paragraphs 2 and 3 were omitted.
3.Article 6 is to be read as if—
(a)in paragraph 1, “Member States shall take appropriate measures to ensure that” were omitted;
(b)after paragraph 1 there were inserted—
Any decision as to whether a substance or object has ceased to be waste must be made—
(a)in accordance with any regulations or [F5assimilated direct] legislation setting out detailed criteria on the application of the conditions in paragraph 1 to specific types of waste; and
(b)having regard to any guidance published by the appropriate authority or the appropriate agency for the purposes of this Article.”;
(c)in paragraph 2—
(i)the first subparagraph were omitted;
(ii)in the second subparagraph, for “Those detailed criteria” there were substituted “Any detailed criteria set out in guidance as referred to in paragraph 1A”;
(iii)the third and fourth subparagraphs were omitted;
(d)paragraph 3 were omitted;
(e)in paragraph 4—
(i)in the first subparagraph—
(aa)in the first sentence, for the words from the beginning to “Member State”, there were substituted “Where criteria have not been set out as referred to in paragraph 1A(a), the appropriate agency”;
(bb)the second sentence were omitted;
(ii)in the second subparagraph—
(aa)for “Member States” there were substituted “The appropriate agency”;
(bb)“by competent authorities” were omitted.
4.Article 7 is to be read as if—
(a)before paragraph 1 there were inserted—
In this Article, the “list of waste” means the list contained in the Annex to Commission Decision 2000/532/EC, as that list has effect in England, Wales, Scotland or Northern Ireland (as the case may be).”;
(b)in paragraph 1—
(i)the first and second sentences were omitted;
(ii)for the third sentence there were substituted “The list of waste shall, except as provided in Commission Decision 2000/532/EC, be binding as regards determination of the waste which is to be considered as hazardous waste or as non-hazardous waste.”;
(c)paragraphs 2, 3, 6 and 7 were omitted
5.Annex 3 is to be read as if, in entry HP 9, in the second sentence, “in the Member States” were omitted.]
Textual Amendments
F4Arts. 1A, 1B inserted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(3)
F5Words in Art. 1B(3)(b) substituted (27.2.2025) by The Retained EU Law (Revocation and Reform) Act 2023 (Consequential Amendments) Regulations 2025 (S.I. 2025/82), reg. 1(2), Sch. 15 para. 135
. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
Textual Amendments
F6Art. 2 omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(4)
Done at Brussels, 21 February 2020.
For the Commission
Virginijus Sinkevičius
Member of the Commission
These guidelines set out elements to be taken into consideration for inspections of [F7mining waste facilities] that are to be carried out by competent authorities in accordance with [F8the inspection provisions]. Such inspections are aimed at ensuring that any waste facility has obtained the required permit and complies with the relevant permit conditions. The inspections relate to the different life-phases of the waste facilities.
Textual Amendments
F7Words in Annex Pt. A substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(5)(a)
F8Words in Annex Pt. A substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(5)(b)
These guidelines address the general framework for carrying out inspections (Part C), the focus of the inspections for each of the different life-phases of the waste facilities (Part D) and the specific elements relevant to inspection of Category A facilities (Part E).
For the purpose of these guidelines, ‘inspection’ means all activities undertaken by a competent authority or on its behalf in order to ensure compliance by [F9mining waste facilities] with the conditions of the permit that they have to obtain. These activities may include in particular:
Textual Amendments
F9Words in Annex Pt. B substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(6)
assessing relevant environmental and safety issues and the risks presented by the waste facilities;
carrying out site visits to check premises, site conditions, relevant equipment, including whether it is adequately maintained, relevant documents and electronic data, internal measures and systems and operating processes;
interviewing staff working at the waste facility;
reinforcing operators’ knowledge of the relevant legal requirements and the environmental impacts of the activities of the operators;
taking samples;
using earth observation techniques and other forms of remote surveillance, including those involving in situ sensors, where appropriate;
verifying operators’ self-monitoring;
checking documents and electronic data, including operator’s reports, other than by means of site visits;
checking operators’ internal measures and systems and operating processes other than by means of site visits;
checking financial guarantees or equivalent;
recording factual information on non-compliance;
identifying the reasons for detected non-compliance and the possible types of impacts of such non-compliance on the environment and human health;
describing detected non-compliance, in particular the circumstances (including the persons) which led to non-compliance, in order to identify, as far as possible, what actions are needed to ensure compliance and enable them, including by cooperating and sharing inspection findings with other relevant competent authorities.
Inspections, including site visits, may be routine, i.e. carried out as part of a regular set of activities, and non-routine, i.e. carried out in response to serious complaints or for the investigation of serious accidents, incidents and other occurrences of non-compliance.
The following shall be taken into consideration:
the availability, for [F10each part of the United Kingdom] and for the full range of [F11mining waste facilities], of competent authorities in charge of inspections;
the independence of the competent authorities and their capacity to fulfil all tasks necessary for carrying out the inspections;
the powers of the competent authorities to carry out inspections, including their right to enter facilities and examine relevant material assets, documents and electronic data;
the sufficiency of the resources, personnel and equipment available to the competent authorities in order to carry out inspections;
the arrangements the competent authorities have in place for co-operation and co-ordination of their activities with other relevant authorities, in particular other authorities with responsibilities in relation to compliance with permits required under F12... environmental legislation that is applicable or relevant to the [F13mining waste facilities];
the level of knowledge, experience and competence that inspectors need to have to carry out inspections, in particular as regards the design, construction, operation and closure of waste facilities;
the organisation of training to update the knowledge that inspectors have;
the necessary assistance that operators must provide to the competent authorities to enable them to carry out inspections, including site visits, the taking of samples and the gathering of information necessary for the performance of their duties pursuant to [F14the inspection provisions].
Textual Amendments
F10Words in Annex Pt C para. 1(a) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(a)(i)(aa)
F11Words in Annex Pt C para. 1(a) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(a)(i)(bb)
F12Words in Annex Pt C para. 1(e) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(a)(ii)(aa)
When carrying out inspections, the competent authorities may be assisted by and may delegate inspection tasks to independent experts in accordance with national legislation, provided that the experts operate under the supervision of the competent authority. The competent authority shall determine the minimum qualifications of the experts and shall assess whether those qualifications are met. The competent authority shall also verify that the experts have no personal interest in the outcome of the inspection.
The following shall be taken into consideration:
planning of inspections in advance by means of a plan or plans established at the appropriate administrative level based on a general assessment of the relevant environmental and safety issues and risks of the waste facilities and, where information is already available on compliance, an overall assessment of the state of compliance for the waste facilities operating within the plan area. Such plans can be integrated or combined with other inspection plans where considered appropriate;
the periodic review and, where appropriate, the updating of the inspection plan or plans;
the coverage in the inspection plan or plans of each [F15mining waste facility];
the inclusion in each inspection plan of the following:
a general assessment of relevant environmental and safety issues and risks;
the geographical area covered by the inspection plan;
a list of the waste facilities covered by the inspection plan which hold a permit;
the means of ensuring identification of [F16mining waste facilities] which operate without a permit;
procedures for carrying out routine inspections;
procedures for carrying out non-routine inspections;
procedures for carrying out announced and unannounced site visits;
where necessary, arrangements on the cooperation and co-ordination between different competent authorities in charge of inspections and between those authorities and other authorities with a role in the enforcement of permits required under F17... environmental legislation that is applicable or relevant to [F18mining waste facilities];
information on the human, financial and other resources needed by the competent authority for the implementation of the inspection plan.
Textual Amendments
F15Words in Annex Pt C para. 2.1(c) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(b)(i)
F16Words in Annex Pt C para. 2.1(d)(iv) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(b)(ii)
F17Words in Annex Pt C para. 2.1(d)(viii) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(b)(iii)(aa)
The following shall be taken into consideration:
the carrying out of routine inspections at regular intervals based on an appropriate risk assessment of the waste facility concerned;
an adequate frequency of site visits based on an appropriate risk assessment of the waste facility concerned, reflecting also the potentially higher risks of Category A facilities;
the application of the following criteria for the risk assessment of the waste facilities:
the potential and actual impacts of the facilities concerned on human health and the environment, taking into account the levels and types of emissions, the sensitivity of the local environment and the risk of accidents as further specified in Best Available Technique (BAT 5) of the BAT Reference Document for the management of wastes from the extractive industries (MWEI BREF)(2);
the previous compliance record;
the participation of the operator of the waste facility in the Environmental Management System (EMS) as further specified in BAT 1 of the MWEI BREF;
the noting by the inspector, where appropriate, of relevant findings of inspections carried out under other applicable F19... legislation;
the provision to the operator, when site visits are announced in advance, of the visit schedule and details of the information, and any other assistance, that the operator will be requested to provide;
in the event of detection of non-compliance or a risk to compliance, the carrying out of an investigation and, as appropriate, the sharing of the results with other authorities, in particular with a view to:
providing a description of the non-compliance or compliance risk, clarifying its causes and impact on the environment and human health, and in particular clarifying the circumstances (including the persons) which led to non-compliance;
providing a factual base to facilitate and enable appropriate responses to address the detected non-compliance and prevent future non-compliance, including, as appropriate, additional inspections, corrective measures by the operator, update of permit conditions, suspension of the permit or use of sanctions;
in the event of the suspension of the operation of a waste facility because of non-compliance with permit conditions, the undertaking of further inspection activities with a view to attaining environmental and other results that the permit conditions were intended to secure.
Textual Amendments
F19Word in Annex Pt. C para. 2.2(d) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(c)
The following shall be taken into consideration:
the carrying out of non-routine inspections, including site visits, as soon as possible after the competent authority receives serious complaints concerning non-compliance with the permit requirements or otherwise becomes aware of serious accidents, incidents or occurrences of non-compliance, irrespective of whether such events need to be notified F20..., in particular with a view to:
clarifying the causes of the event, its impacts on the environment and human health, and in particular clarifying the circumstances (including the persons) which led to non-compliance;
providing a factual base to facilitate and enable appropriate responses to address the detected non-compliance and prevent future accidents, incidents or occurrences of non-compliance, including, as appropriate, additional inspections, corrective measures by the operator, update of permit conditions, suspension of the permit or use of sanctions;
the noting by the inspector, where appropriate, of relevant findings of inspections carried out under other applicable F21... legislation;
the carrying out of non-routine inspections as soon as possible with respect to, and, where appropriate, before the reconsideration or update of a permit.
Textual Amendments
F20Words in Annex Pt C para. 2.3(a) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(d)(i)
F21Word in Annex Pt C para. 2.3(b) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(d)(ii)
The following shall be taken into consideration:
the undertaking of an appropriate number of unannounced site visits, in particular where relevant to the detection of problems or risk exposure or the need to respond to an urgent situation;
as far as practicable, the addressing, in decisions on unannounced site visits, of health, environmental and safety concerns and of the possible need for the waste facility’s operational staff to be on site.
The following shall be taken into consideration:
the appropriate documentation of all inspection activities;
the preparation, after each site visit to a waste facility, of a site visit report that is recorded in writing and stored in identifiable form in a readily accessible and adequately maintained database;
the inclusion in the site visit report of the purpose of the inspection, the data, information and findings gathered, an evaluation thereof and a conclusion on whether the waste facility complies with the relevant conditions of the permit and whether any further action should follow;
the completion of the site visit report within two months after the site visit, unless more serious findings have been made during the site visit, in which case another deadline may be required;
the provision to the operator, before or after the finalisation of the site visit report, of an opportunity to submit comments, where appropriate;
the availability to the public of the results of the site visit and, as appropriate, of other inspection activities, in accordance with [F22the Environmental Information Regulations 2004 or the Environmental Information (Scotland) Regulations 2004].
Textual Amendments
F22Words in Annex Pt C para. 3.1(f) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(7)(e)
The following shall be taken into consideration for the purposes of the inspection:
the implementation of the measures taken in order to minimise environmental impact during operation and after closure, including, if required, handling of contaminated water and leachate;
the compliance of the location, design and construction of the waste facility with the safety and environmental elements given in the permit;
the content, availability and performance of the self-monitoring system for regular monitoring and operators self-inspections and of the planned reporting of the monitoring data to the competent authority;
the implementation of the management, maintenance and surveillance measures planned to ensure the physical stability of the facility and to prevent pollution or contamination of soil, air, surface water or groundwater in the short and long-term perspectives as well as to minimise as far as possible damage to the landscape;
the availability of sufficient human resources and the competence of the personnel in charge of the environmental management and safety of the waste facility;
the adequacy of the plan for closure [F23contained in the waste management plan for the waste facility];
the adequacy of the financial guarantee or equivalent with regard to its amount and form, where the competent authority requires a financial guarantee or equivalent; whether the classification of the waste facility as a Category A facility or not a Category A facility needs to be reviewed and verified;
the compliance with any other permit conditions and any other relevant requirements [F24under the relevant mining waste legislation].
Textual Amendments
F23Words in Annex Pt D para. 1(f) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(a)(i)
F24Words in Annex Pt D para. 1(h) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(a)(ii)
The following shall be taken into consideration for the purposes of the inspection:
adverse effects of the waste facility on the environment and human health and measures taken in order to minimise environmental impact; in particular, suitability of the construction, management and maintenance of the waste facility to ensure its physical stability and to prevent pollution or contamination of soil, air, surface water or groundwater in the short and long-term perspectives as well as to minimise as far as possible damage to landscape and how these effects correspond to the permit conditions and the information in the environmental impact assessment if such an assessment is required;
the compliance of the quantities, characteristics and classification of the waste deposited in the waste facility with the elements given in the permit;
the compliance of the estimated leachate generation, including the contaminant content of the leachate, of the deposited waste, and of the water balance of the waste facility with the elements given in the permit;
structural and operational changes of the waste facility: checking of (1) the water management, (2) the quality of geotechnical construction activities (e.g. raised dam/embankment construction), (3) the management of geotechnical safety systems (e.g. surface coverings, stability and safety monitoring), (4) quantities and characteristics of the waste deposited in comparison to projections in the waste management plan, (5) leachate generation including contaminant content of the leachate in comparison to projections in the waste management plan, (6) the water balance of the waste facility in comparison to projections in the waste management plan, and (7) techniques used for, and the adequacy of, the environmental and safety management and the environmental monitoring;
the adoption of measures recommended or imposed after previous inspections;
the environmental and safety audit reports and statements if required in the permit;
results, completeness, management and performance of the self-monitoring programme for regular monitoring and of the reporting of all monitoring data (if applicable) to the competent authority;
visual abnormalities of the site;
the representativeness of the sampling and characterization of extractive waste;
roles, responsibilities and competence of personnel in charge of the environmental and safety management of the waste facility as well as availability of sufficient human resources and training provided to staff;
procedures for notifying the competent authority of any events likely to affect the stability of the waste facility, and any significant adverse environmental effects revealed by the relevant control and monitoring procedures;
the adequacy of the plan for closure [F25contained in the waste management plan for the waste facility] and compliance with any progressive closure measures specified in the plan;
the adequacy of the amount and form of the financial guarantee or equivalent in respect of the calculated costs for the obligations of the operator under the permit, including closure and after-closure arrangements and rehabilitation of the land affected, where the competent authority requires a financial guarantee or equivalent;
the classification of the waste facility as a Category A facility or not a Category A facility;
the compliance with any other permit conditions and any other relevant requirements [F26under the relevant mining waste legislation].
Textual Amendments
F25Words in Annex Pt D para. 2(l) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(b)(i)
F26Words in Annex Pt D para. 2(o) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(b)(ii)
The following shall be taken into consideration for the purposes of the inspection:
adverse effects on the environment and human health from the waste facility and the measures taken in order to minimise such impact after closure, including, if required, the handling of contaminated water and leachate;
the implementation of the plan for closure [F28contained in the waste management plan for the waste facility];
the rehabilitation of the land affected by the waste facility;
the adequacy of the plan and arrangements for the maintenance, monitoring, control and corrective measures in the after-closure phase of the waste facility, including the functioning and the adequacy of the monitoring, surveillance and control equipment;
the adequacy of the amount and form of the financial guarantee or equivalent in respect of the calculated costs for the obligations of the operator under the permit, including completion of closure and after-closure arrangements and remaining rehabilitation of the land affected, where the competent authority requires a financial guarantee or equivalent;
the classification of the waste facility as a Category A facility or not a Category A facility;
the compliance with any other permit conditions and with any other relevant requirements [F29under the relevant mining waste legislation].
Textual Amendments
F28Words in Annex Pt D para. 3(b) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(c)(ii)
F29Words in Annex Pt D para. 3(g) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(c)(iii)
Textual Amendments
F27Words in Annex Pt D para. 3 heading omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(c)(i)
The following shall be taken into consideration for the purposes of the inspection:
adverse effects on the environment and human health from the waste facility and the measures taken in order to minimise such impact after closure, including, if required, the handling of contaminated water and leachate;
the correspondence between, on the one hand, the adverse effects referred to in point (a) and, on the other hand, the permit conditions and the information in the environmental impact assessment, if required;
the compliance of the leachate generation, including the contaminant content of the leachate, of the deposited waste, and of the water balance of the waste facility and, if required, the handling of contaminated water and leachate with the elements given in the permit;
the implementation of the plan for closure [F30contained in the waste management plan for the waste facility];
the adequacy of the plan for closure F31..., in particular as regards the need for additional closure and rehabilitation measures based on environmental risk and impact evaluation;
the rehabilitation of the land affected by the waste facility; the adequacy of the plan and arrangements for the maintenance, monitoring, control and corrective measures in the after-closure phase of the waste facility, including functioning and the adequacy of the monitoring, surveillance and control equipment, and of the reporting of all monitoring data to the competent authority;
procedure for notifying the competent authority of any events or developments likely to affect the stability of the waste facility, and of any significant adverse environmental effects revealed by the relevant control and monitoring procedures;
the adequacy of the amount and form of the financial guarantee or equivalent with in respect of the calculated costs for the obligations under the permit, including completion of after-closure arrangements, corrective measures and rehabilitation of the land affected, where the competent authority requires a financial guarantee or equivalent;
the classification of the waste facility as a Category A facility or not a Category A facility;
the compliance with any other permit conditions, and any other relevant requirements [F32under the relevant mining waste legislation].
Textual Amendments
F30Words in Annex Pt para. 4(d) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(d)(i)
F31Words in Annex Pt para. 4(e) omitted (31.12.2020) by virtue of The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(d)(ii)
F32Words in Annex Pt para. 4(j) substituted (31.12.2020) by The Waste and Environmental Permitting etc. (Legislative Functions and Amendment etc.) (EU Exit) Regulations 2020 (S.I. 2020/1540), regs. 1(2), 17(8)(d)(iii)
In addition to the relevant elements listed in Part D, the following shall be taken into consideration by the inspector where the inspection concerns dams of Category A waste facilities containing tailings:
type and condition of erosion protection;
adequacy of the hydrological design, such as water balance, available free-board (vertical distance (height) between the normal maximum operating level of a pond and the crest of the dam);
composition, status and structural integrity of the beach, such as presence of depressions, tailings density, dust control;
changes of the dam’s crest and slope comparing the current state versus the design state;
functioning and condition of the drainage system and its state and geotechnical structures (such as geomembranes, dams) and equipment (such as dam structure monitoring);
leakage and seepage areas, and amount of material leaked;
any detected damages;
trees and vegetation on the dam.
In addition to the relevant elements listed in Part D, the following shall be taken into consideration by the inspector where the inspection concerns discharge arrangements of Category A waste facilities containing tailings and the functioning of such discharge arrangements:
adequacy of access to discharge lines and discharge points;
damages of construction and control equipment;
leakage through and around the discharge arrangements;
erosion of downstream outlet;
vegetation in or close to the discharge arrangements;
discharge regulation equipment;
emergency discharge arrangements;
back-up power supply;
rate of increase of discharges to the tailings pond and related rate of increase of the pond level (measured in meters/year);
tailings placement system;
water management system.
In addition to the relevant elements listed in Part D, the following shall be taken into consideration by the inspector where the inspection concerns Category A waste facilities that contain waste rocks:
weathering of the rocks;
seepage water quality and quantity;
whether the measures taken to minimise the environmental impacts of waste rock facilities are adequate;
correctness and effectiveness of recultivation activities based on relevant legal obligations.
http://eippcb.jrc.ec.europa.eu/reference/BREF/jrc109657_mwei_bref_-_for_pubsy_online.pdf
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: