When the UK left the EU, legislation.gov.uk published EU legislation that had been published by the EU up to IP completion day (31 December 2020 11.00 p.m.). On legislation.gov.uk, these items of legislation are kept up-to-date with any amendments made by the UK since then.
Legislation.gov.uk publishes the UK version. EUR-Lex publishes the EU version. The EU Exit Web Archive holds a snapshot of EUR-Lex’s version from IP completion day (31 December 2020 11.00 p.m.).
This version of this Decision was derived from EUR-Lex on IP completion day (31 December 2020 11:00 p.m.). It has not been amended by the UK since then. Find out more about legislation originating from the EU as published on legislation.gov.uk.![]()
Revised legislation carried on this site may not be fully up to date. At the current time any known changes or effects made by subsequent legislation have been applied to the text of the legislation you are viewing by the editorial team. Please see ‘Frequently Asked Questions’ for details regarding the timescales for which new effects are identified and recorded on this site.
THE EUROPEAN COMMISSION,
Having regard to the Treaty on the Functioning of the European Union,
Having regard to Regulation (EC) No 715/2009 of the European Parliament and of the Council of 13 July 2009 on conditions for access to the natural gas transmission networks and repealing Regulation (EC) No 1775/2005(1), and in particular Article 23(2) thereof,
Whereas:
(1) Regulation (EC) No 715/2009 sets non-discriminatory rules for access conditions to natural gas transmission systems to ensure the proper functioning of the internal market in gas. Since the duplication of gas transmission systems is in most cases not economic and efficient, competition in natural gas markets is stimulated by third-party access opening infrastructure to all suppliers in a transparent and non-discriminatory way. The frequent occurrence of contractual congestion where network users cannot gain access to gas transmission systems in spite of the physical availability of the capacity is an obstacle on the road towards completing the internal energy market.
(2) The practice has shown that despite the application of certain congestion-management principles such as the offering of interruptible capacities as provided for by Regulation (EC) No 1775/2005 of the European Parliament and of the Council of 28 September 2005 on conditions for access to the natural gas transmission networks(2) and Regulation (EC) No 715/2009, contractual congestion in the Union gas transmission networks remains an obstacle to the development of a well-functioning internal market in gas. Therefore it is necessary to amend the guidelines on the application of congestion-management procedures in the event of contractual congestion. In accordance with Article 23(3) of Regulation (EC) No 715/2009 the proposed guidelines should reflect differences between national gas systems and may set minimum requirements to be met to achieve non-discriminatory and transparent network access conditions with respect to congestion management procedures.
(3) The congestion-management procedures should apply in the event of contractual congestion and are aimed at resolving those events by bringing unused capacity back to the market to be reallocated in the course of the regular allocation processes.
(4) Where an interconnection point is frequently subject to the occurrence of physical congestion, congestion management procedures may often be of no avail. In those cases a solution should be examined from a network planning and investment point of view.
(5) In accordance with Regulation (EC) No 713/2009 of the European Parliament and of the Council(3) the Agency for the Cooperation of Energy Regulators (‘the Agency’) should monitor and analyse the implementation of these guidelines. It is necessary that transmission system operators publish the information necessary to identify the occurrence of contractual congestion in a workable format.
(6) In accordance with Article 24 of Regulation (EC) No 715/2009 the national regulatory authorities ensure compliance with those guidelines.
(7) In order to ensure that congestion management procedures are applied in the most effective way at all interconnection points and with a view to maximising available capacities in all adjacent entry-exit systems, it is of great importance that national regulatory authorities and transmission system operators from different Member States and within Member States closely cooperate amongst themselves and with each other. In particular national regulatory authorities and transmission system operators should have regard to best practices and endeavour to harmonise processes for the implementation of these Guidelines. Acting in accordance with Article 7 of Regulation (EC) No 713/2009 the Agency and the national regulatory authorities should ensure that the most effective congestion management procedures are implemented at the applicable entry and exit points across the Union.
(8) Whereas transmission system operators possess detailed information about the physical use of the system and are best placed to assess future flows, it is appropriate for them to determine an amount of additional capacity to be made available in addition to the calculated technical capacity. By offering more firm capacity than technically available through taking into consideration flow scenarios and contracted capacities, transmission system operators take a risk that should be rewarded accordingly. For the purpose of determining transmission system operators’ revenues, such additional capacity should however only be allocated if all other capacity, including capacity resulting from the application of other congestion-management procedures, has been allocated. Transmission system operators should closely cooperate to set the technical capacity. In order to resolve a potential situation of physical congestion the transmission system operators should apply the most cost-effective measure, including either buying back capacity or taking other technical or commercial measures.
(9) Regulation (EC) No 715/2009 should therefore be amended accordingly.
(10) The measures provided for in this Decision are in accordance with the opinion of the Committee established by Article 51 of Directive 2009/73/EC of the European Parliament and of the Council(4),
HAS ADOPTED THIS DECISION:
Annex I to Regulation (EC) No 715/2009 is amended in accordance with the Annex to this Decision.
This Decision shall enter into force on the twentieth day following that of its publication in the Official Journal of the European Union.
Done at Brussels, 24 August 2012.
For the Commission
The President
José Manuel Barroso
Annex I to Regulation (EC) No 715/2009 is amended as follows:
point 2.2 is replaced by the following:
for at least three firm capacity products with a duration of one month or
for at least two firm capacity products with a duration of one quarter or
for at least one firm capacity product with a duration of one year or more or
where no firm capacity product with a duration of one month or more has been offered.
Transmission system operators shall accept any surrender of firm capacity which is contracted by the network user at an interconnection point, with the exception of capacity products with a duration of a day and shorter. The network user shall retain its rights and obligations under the capacity contract until the capacity is reallocated by the transmission system operator and to the extent the capacity is not reallocated by the transmission system operator. Surrendered capacity shall be considered to be reallocated only after all the available capacity has been allocated. The transmission system operator shall notify the network user without delay of any reallocation of its surrendered capacity. Specific terms and conditions for surrendering capacity, in particular for cases where several network users surrender their capacity, shall be approved by the national regulatory authority.
the network user uses less than on average 80 % of its contracted capacity both from 1 April until 30 September and from 1 October until 31 March with an effective contract duration of more than one year for which no proper justification could be provided; or
the network user systematically nominates close to 100 % of its contracted capacity and renominates downwards with a view to circumventing the rules laid down in point 2.2.3(3).
point 3.1.1(1) is amended as follows:
point (e) is replaced by the following:
in a downloadable format that has been agreed between transmission system operators and the national regulatory authorities — on the basis of an opinion on a harmonised format that shall be provided by the Agency — and that allows for quantitative analyses;’;
the following point (h) is added:
all data shall be made available as of 1 October 2013 on one Union-wide central platform, established by ENTSOG on a cost-efficient basis.’;
in point 3.3(1) the following points (h), (i), (j), (k) and (l) are added:
occurrence of unsuccessful, legally valid requests for firm capacity products with a duration of one month or longer including the number and volume of the unsuccessful requests; and
in the case of auctions, where and when firm capacity products with a duration of one month or longer have cleared at prices higher than the reserve price;
where and when no firm capacity product with a duration of one month or longer has been offered in the regular allocation process;
total capacity made available through the application of the congestion-management procedures laid down in points 2.2.2, 2.2.3, 2.2.4 and 2.2.5 per applied congestion-management procedure;
points (h) to (k) shall apply from 1 October 2013.’.
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area.
Original (As adopted by EU): The original version of the legislation as it stood when it was first adopted in the EU. No changes have been applied to the text.
Geographical Extent: Indicates the geographical area that this provision applies to. For further information see ‘Frequently Asked Questions’.
Show Timeline of Changes: See how this legislation has or could change over time. Turning this feature on will show extra navigation options to go to these specific points in time. Return to the latest available version by using the controls above in the What Version box.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
This timeline shows the different versions taken from EUR-Lex before exit day and during the implementation period as well as any subsequent versions created after the implementation period as a result of changes made by UK legislation.
The dates for the EU versions are taken from the document dates on EUR-Lex and may not always coincide with when the changes came into force for the document.
For any versions created after the implementation period as a result of changes made by UK legislation the date will coincide with the earliest date on which the change (e.g an insertion, a repeal or a substitution) that was applied came into force. For further information see our guide to revised legislation on Understanding Legislation.
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: