(1)Where there has been a breach of planning control of a description set out in the first column of the Table, no enforcement action may be taken in respect of the breach after the end of the period specified in the corresponding entry in the second column.
| Description of breach of planning control | Period for taking enforcement action |
|---|---|
| Carrying out operations on land without planning permission | 4 years beginning with the day the operations were substantially completed |
| Making a change in the use of a building to use as a dwelling or (if the building was previously used as one or more dwellings) to use as a different number of dwellings | 4 years beginning with the day the breach took place |
| Any other breach of planning control | 10 years beginning with the day the breach took place |
(2)Subsection (1) does not prevent—
(a)a breach of condition notice being served in respect of a breach of planning control at any time when an enforcement notice has effect in respect of the breach;
(b)enforcement action being taken in respect of a breach of planning control during the 4 years beginning with the day any other enforcement action (or purported enforcement action) was taken in respect of the breach.
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download.
Would you like to continue?
The Whole Act you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Whole Act without Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
The Schedules you have selected contains over 200 provisions and might take some time to download. You may also experience some issues with your browser, such as an alert box that a script is taking a long time to run.
Would you like to continue?
Latest Available (revised):The latest available updated version of the legislation incorporating changes made by subsequent legislation and applied by our editorial team. Changes we have not yet applied to the text, can be found in the ‘Changes to Legislation’ area. The revised version is currently only available in English.
Original (As Enacted or Made) - English: The original English language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Original (As Enacted or Made) - Welsh:The original Welsh language version of the legislation as it stood when it was enacted or made. No changes have been applied to the text.
Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:
Use this menu to access essential accompanying documents and information for this legislation item. Dependent on the legislation item being viewed this may include:
Click 'View More' or select 'More Resources' tab for additional information including: