10.Section 3 states the circumstances in which development related to liquified natural gas facilities will be a Significant Infrastructure Project. These are:

  • for the construction of a facility in Wales or the Welsh marine area, the storage capacity is expected to be at least 43 million standard cubic metres or have a maximum flow rate of at least 4.5 million standard cubic metres per day;

  • for the alteration of a facility in Wales or the Welsh marine area, the existing storage capacity is expected to increase by at least 43 million standard cubic metres or by a maximum flow rate of at least 4.5 million standard cubic metres more per day.

Back to top

Options/Help

Print Options

Close

Explanatory Notes

Text created by the Welsh Government department responsible for the subject matter of the Act to explain what the Act sets out to achieve and to make the Act accessible to readers who are not legally qualified. Explanatory Notes accompany all Acts of Senedd Cymru.

Close

More Resources

Access essential accompanying documents and information for this legislation item from this tab. Dependent on the legislation item being viewed this may include:

  • the original print PDF of the as enacted version that was used for the print copy
  • lists of changes made by and/or affecting this legislation item
  • confers power and blanket amendment details
  • all formats of all associated documents
  • correction slips
  • links to related legislation and further information resources